United States › Grid › Interconnection queues › California

GAS · CAISO

Wellhead Power Margarita

Wellhead Power Margarita is a 49.9 MW gas request withdrawn in the CAISO interconnection queue, in Orange County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2007 (completed)
  2. Withdrawn / abandonedApr 2008 (project stopped here)
  3. ConsentedApr 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
176
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Margarita 138kV Substation
Location
Orange County, California
Technology
Gas: 49.9 MW
Total requested
49.9 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
23 February 2007
Agreement signed
29 April 2008
Proposed online date
June 2010
Withdrawn
April 2008

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Orange County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem