United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2020 requests) โ€” page 34

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests ยท page 34 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Old Baptist Road Substation - NG Western RI DG Area Study
Solar
4.4 MWWithdrawn / abandoned Washington, RIISO-NE Mar 2020target 2021
Johnston Substation - NG Western RI DG Area Study
Solar
4.3 MWWithdrawn / abandoned Providence, RIISO-NE Mar 2020target 2021
Old Baptist Road - NG WRI DG Area Study #2 <5 MW
Solar
4.0 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2022
Solar project AG1-200, Bergen County
Solar
4.0 MWWithdrawn / abandoned Bergen, NJPJM Sep 2020target 2021
Solar
Solar
4.0 MWWithdrawn / abandoned Washington, MEISO-NE Apr 2020target 2021
Gas project AF2-158, Prince George's County
Gas
4.0 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2020target 2021
Solar project AF2-104, Somerset County
Solar
4.0 MWWithdrawn / abandoned Somerset, PAPJM Feb 2020target 2020
Solar project AF2-230, Montgomery County
Solar
4.0 MWWithdrawn / abandoned Montgomery, PAPJM Mar 2020target 2020
Solar project AG1-335, Mercer County
Solar
4.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2020target 2022
Solar + storage project AG1-520, Somerset County
Solar + storage
4.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2020target 2022
Solar project AG1-252, Mercer County
Solar
3.9 MWWithdrawn / abandoned Mercer, PAPJM Sep 2020target 2021
Wind + storage project 1216, Salt Lake County
Wind + storage
3.9 MWWithdrawn / abandoned Salt Lake, UTWest Apr 2020
Drumrock - NG Western RI DG Area Study
Solar
3.8 MWWithdrawn / abandoned Kent, RIISO-NE Mar 2020target 2021
Wind
Onshore wind
3.8 MWWithdrawn / abandoned Litchfield, CTISO-NE Mar 2020target 2024
Solar + storage project AF2-269
Solar + storage
3.7 MWWithdrawn / abandoned PAPJM Mar 2020target 2021
Solar + storage project AG1-077, Magoffin County
Solar + storage
3.7 MWWithdrawn / abandoned Magoffin, KYPJM Jul 2020target 2022
BE-Chalybeate
Solar + storage
3.7 MWWithdrawn / abandoned Bedford, PAPJM Mar 2020target 2022
BR-Mountain View
Solar + storage
3.7 MWWithdrawn / abandoned Berks, PAPJM Mar 2020target 2022
Battery storage project AF2-098, Grant County
Battery storage
3.5 MWWithdrawn / abandoned Grant, KYPJM Feb 2020target 2020
Kenyon Substation - NG Western RI DG Area Study
Solar
3.5 MWWithdrawn / abandoned Washington, RIISO-NE Mar 2020target 2021
Hopkins Hill - NG WRI DG Area Study #2 <5 MW
Solar
3.5 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2022
Gas project AF2-160, Allegheny County
Gas
3.5 MWWithdrawn / abandoned Allegheny, PAPJM Mar 2020target 2020
Solar + battery
Solar + storage
3.2 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2020target 2023
Tower Hill - NG WRI DG Area Study #2 <5 MW
Solar
3.1 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2025
BL-Kettle
Solar + storage
3.0 MWWithdrawn / abandoned Blair, PAPJM Mar 2020target 2022
Solar project AG1-300, Cumberland County
Solar
3.0 MWWithdrawn / abandoned Cumberland, NJPJM Sep 2020target 2021
BR-Swissdale
Solar + storage
3.0 MWWithdrawn / abandoned Blair, PAPJM Mar 2020target 2022
CL-Route 58 R
Solar + storage
3.0 MWWithdrawn / abandoned Clarion, PAPJM Mar 2020target 2022
LA-Blue Rock
Solar + storage
3.0 MWWithdrawn / abandoned Lancaster, PAPJM Mar 2020target 2023
Solar project AG2-028, Adams County
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2020target 2021
Battery storage project AG1-149, Somerset County
Battery storage
3.0 MWWithdrawn / abandoned Somerset, MDPJM Sep 2020target 2021
Solar project AG1-299, Atlantic County
Solar
3.0 MWWithdrawn / abandoned Atlantic, NJPJM Sep 2020target 2021
Solar project AG2-022, Dauphin County
Solar
3.0 MWWithdrawn / abandoned Dauphin, PAPJM Oct 2020target 2021
LH-Decatur
Solar + storage
3.0 MWWithdrawn / abandoned Lehigh, PAPJM Mar 2020target 2026
LA-Buck
Solar + storage
3.0 MWWithdrawn / abandoned Lancaster, PAPJM Mar 2020target 2023
PE-Windy Hill
Solar + storage
3.0 MWWithdrawn / abandoned Perry, PAPJM Mar 2020target 2023
PA York Hess
Solar
3.0 MWWithdrawn / abandoned York, PAPJM Mar 2020target 2022
Solar project AG2-026, Berks County
Solar
3.0 MWWithdrawn / abandoned Berks, PAPJM Oct 2020target 2021
PA Adams Ramsburg
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Jan 2020target 2025
Solar project AG2-025, Cumberland County
Solar
3.0 MWWithdrawn / abandoned Cumberland, PAPJM Oct 2020target 2021
Solar project AG2-027, Adams County
Solar
3.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2020target 2021
PE-Dellville
Solar + storage
3.0 MWWithdrawn / abandoned Perry, PAPJM Mar 2020target 2024
Ritner Solar
Solar
3.0 MWWithdrawn / abandoned Cumberland, PAPJM Mar 2020target 2023
Solar project AG2-023, Cumberland County
Solar
3.0 MWWithdrawn / abandoned Cumberland, PAPJM Oct 2020target 2021
FR-Statler
Solar + storage
3.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2020target 2026
FR-Social Island
Solar + storage
3.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2020target 2026
BR-Allentown
Solar + storage
3.0 MWWithdrawn / abandoned Berks, PAPJM Mar 2020target 2022
BR-Water
Solar + storage
3.0 MWWithdrawn / abandoned Berks, PAPJM Mar 2020target 2022
PA Cumberland Diehl
Solar
3.0 MWWithdrawn / abandoned Cumberland, PAPJM Jan 2020target 2022
PE-Green Park
Solar + storage
3.0 MWWithdrawn / abandoned Perry, PAPJM Mar 2020target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)