United States › Grid › Interconnection queues › Pennsylvania
SOLAR + STORAGE · PJMLA-Blue Rock
LA-Blue Rock is a 3.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Lancaster County, Pennsylvania, connecting to PPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-279
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Letort 12.47 kV
- Location
- Lancaster County, Pennsylvania
- Technology
- Solar: 3.0 MW · Battery
- Total requested
- 3.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 27 March 2020
- Proposed online date
- February 2023
- Withdrawn
- November 2023
Location
Marker shows the centre of Lancaster County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Lancaster County
- HoltwoodHydro · 140 MW · built
- HoltwoodHydro · 107 MW · built
- Dart ContainerOther · 11.4 MW · built
- YorkGas · 10.0 MW · built
- Keystone SolarSolar · 5.0 MW · built
- Turkey Hill Dairy WFOnshore wind · 3.2 MW · built
- HoltwoodHydro · 2.0 MW · built
- Granger of HoneybrookOther · 1.6 MW · built
- Sight and Sound TheaterGas · 1.6 MW · built
- ElizabethtownGas · 0.3 MW · built
- Gas project AA2-109, Lancaster CountyGas · 1,100 MW · withdrawn
- Gas project U1-016, Lancaster CountyGas · 700 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem