United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· PJMPA York Hess
PA York Hess is a 3.0 MW solar request withdrawn in the PJM interconnection queue, in York County, Pennsylvania, connecting to ME.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-151
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ME
- Connection point (POI)
- Dillsburg 13.2 kV
- Location
- York County, Pennsylvania
- Technology
- Solar: 3.0 MW
- Total requested
- 3.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 16 March 2020
- Proposed online date
- September 2022
- Withdrawn
- October 2024
Location
Marker shows the centre of York County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in York County
- Peach Bottom Units #2 & #3Nuclear Β· 44.0 MW Β· agreement signed
- Battery storage project AH2-335, York CountyBattery storage Β· 130 MW Β· in study
- Strinestown Solar ProjectSolar Β· 79.6 MW Β· suspended
- Dover SolarSolar Β· 55.0 MW Β· suspended
- Dover SolarSolar Β· 20.0 MW Β· suspended
- Delta YorkGas Β· 760 MW Β· built
- DeltaGas Β· 550 MW Β· built
- Peach Bottom Units 2 & 3Nuclear Β· 206 MW Β· built
- Muddy RunHydro Β· 160 MW Β· built
- Peach Bottom - Units 2 & 3Nuclear Β· 140 MW Β· built
- Delta YorkGas Β· 120 MW Β· built
- Peach Bottom 2 & 3Nuclear Β· 70.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem