SOLAR · PJMPA Cumberland Diehl
PA Cumberland Diehl is a 3.0 MW solar request withdrawn in the PJM interconnection queue, in Cumberland County, Pennsylvania, connecting to ME.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2020 (completed)
- Withdrawn / abandonedApr 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-101
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ME
- Connection point (POI)
- Allen 13.2 kV
- Location
- Cumberland County, Pennsylvania
- Technology
- Solar: 3.0 MW
- Total requested
- 3.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 28 January 2020
- Proposed online date
- September 2022
- Withdrawn
- April 2024
Location
Marker shows the centre of Cumberland County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Cumberland County
- Gobbler KnobSolar · 20.0 MW · agreement signed
- Solar project AG2-166, Cumberland CountySolar · 10.0 MW · in study
- Cumberland County LFOther · 6.4 MW · built
- Cumberland County LandfillOther · 4.8 MW · built
- Mountain Station Unit C2Gas · 1.0 MW · built
- Solar project W3-068, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project AE2-252, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project W2-096, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project X2-004, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project X2-005, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project X4-010, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project Y2-061, Cumberland CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem