United States › Grid › Interconnection queues › Pennsylvania

SOLAR + STORAGE · PJM

CL-Route 58 R

CL-Route 58 R is a 3.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Clarion County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandonedAug 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF2-273
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Sligo 25 kV
Location
Clarion County, Pennsylvania
Technology
Solar: 3.0 MW · Battery
Total requested
3.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
27 March 2020
Proposed online date
September 2022
Withdrawn
August 2022

Location

Marker shows the centre of Clarion County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Clarion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem