United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
SOLAR + STORAGE Β· PJMSolar + storage project AG1-077, Magoffin County
Solar + storage project AG1-077, Magoffin County is a 3.7 MW solar + storage request withdrawn in the PJM interconnection queue, in Magoffin County, Kentucky, connecting to PENELEC.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2020 (completed)
- Withdrawn / abandonedSep 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-077
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- Allegheny Tunnel 23 kV
- Location
- Magoffin County, Kentucky
- Technology
- Solar: 3.7 MW Β· Battery
- Total requested
- 3.7 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 31 July 2020
- Proposed online date
- May 2022
- Withdrawn
- September 2021
Location
Marker shows the centre of Magoffin County; the queue data does not give exact sites.
Other requests in Magoffin County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem