SOLAR + STORAGE Β· PJMLH-Decatur
LH-Decatur is a 3.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Lehigh County, Pennsylvania, connecting to ME.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedApr 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-281
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ME
- Connection point (POI)
- Lynnville 13.2 kV
- Location
- Lehigh County, Pennsylvania
- Technology
- Solar: 3.0 MW Β· Battery
- Total requested
- 3.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 27 March 2020
- Proposed online date
- April 2026
- Withdrawn
- April 2024
Location
Marker shows the centre of Lehigh County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Lehigh County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem