🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 310

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 310 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-052, Mecklenburg County
Solar
60.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Jul 2021target 2025
Solar project J3010, Clay County
Solar
60.0 MWWithdrawn / abandoned Clay, INMISO Sep 2022target 2027
Solar project 998, Tooele County
Solar
60.0 MWWithdrawn / abandoned Tooele, UTWest Jan 2018target 2021
East Hampton Solar
Solar · East Hampton Solar Farm, LLC
60.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jun 2014
Kce NY 26
Battery storage · KCE NY 26, LLC
60.0 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2020
Other project G226.1, Ingham County
Other
60.0 MWWithdrawn / abandoned Ingham, MIMISO Apr 2002target 2004
Solar project AC1-156, Pulaski County
Solar
60.0 MWWithdrawn / abandoned Pulaski, VAPJM Oct 2016target 2019
Solar + storage project Q373, Coconino County
Solar + storage
60.0 MWWithdrawn / abandoned Coconino, AZWest Mar 2021target 2024
Gage Solar
Solar · SunPower
60.0 MWWithdrawn / abandoned ERCOT Sep 2013target 2016
Caden Energix Spout Spring
Solar
60.0 MWWithdrawn / abandoned Appomattox, VAPJM Jul 2018target 2025
Gas project X4-007, Charles County
Gas
60.0 MWWithdrawn / abandoned Charles, MDPJM Nov 2011target 2015
West FRY Wind Energy Project
Onshore wind
60.0 MWWithdrawn / abandoned San Bernardino, CACAISO Sep 2005target 2010
Onshore wind project Q72, Bradford County
Onshore wind
60.0 MWWithdrawn / abandoned Bradford, PAPJM Jul 2006target 2010
Arthur Kill Energy Storage 2
Battery storage · NRG Arthur Kill Storage LLC
60.0 MWWithdrawn / abandoned Richmond, NYNYISO Apr 2019
Battery storage project J1871, Tangipahoa Parish County
Battery storage
60.0 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Aug 2021target 2024
Solar project 610, Mcnairy County
Solar
60.0 MWWithdrawn / abandoned Mcnairy, TNSoutheast Mar 2024
Onshore wind project GEN-2007-049, Beckham County
Onshore wind
60.0 MWWithdrawn / abandoned Beckham, OKSPP Oct 2007target 2009
Solar project 923, Walla Walla County
Solar
60.0 MWWithdrawn / abandoned Walla Walla, WAWest Aug 2017target 2019
Onshore wind project P39, Stark County
Onshore wind
60.0 MWWithdrawn / abandoned Stark, ILPJM Dec 2005target 2008
Onshore wind project GEN-2009-068, Donley County
Onshore wind
60.0 MWWithdrawn / abandoned Donley, TXSPP Dec 2009target 2010
Solar + storage project AG2-179, Adair County
Solar + storage · Round Trip, LLC
60.0 MWWithdrawn / abandoned Adair, KYPJM Mar 2025target 2023
Onshore wind project GEN-2009-006, Washington County
Onshore wind
60.0 MWWithdrawn / abandoned Washington, ARSPP Feb 2009target 2010
Gas project G844, Brookings County
Gas
60.0 MWWithdrawn / abandoned Brookings, SDMISO Feb 2011target 2011
Solar + storage project J1810, White County
Solar + storage
60.0 MWWithdrawn / abandoned White, INMISO Jun 2020target 2023
Solar project AF1-308, Pike County
Solar
60.0 MWWithdrawn / abandoned Pike, OHPJM Sep 2019target 2023
Battery storage project AH1-447, Pittsylvania County
Battery storage · Cascade Energy Storage, LLC
60.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Sep 2021target 2024
Onshore wind project 327, Twin Falls County
Onshore wind
60.0 MWWithdrawn / abandoned Twin Falls, IDWest Mar 2010
Solar project AE2-186, Fauquier County
Solar
60.0 MWWithdrawn / abandoned Fauquier, VAPJM Mar 2019target 2020
Solar project J3217, Cottonwood County
Solar
60.0 MWWithdrawn / abandoned Cottonwood, MNMISO Sep 2022target 2026
Pandora Solar
Solar
60.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2014target 2018
Solar project 20240829006, Colleton County
Solar
60.0 MWWithdrawn / abandoned Colleton, SCSoutheast target 2027
Shockoe Solar Farm
Solar · Zenith Solar, LLC
60.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Mar 2019target 2020
Solar project BHCT G20, Pueblo County
Solar · Black Hills Electric Generation LLC
60.0 MWWithdrawn / abandoned Pueblo, COWest Nov 2015target 2022
Elkwood Solar
Solar
60.0 MWWithdrawn / abandoned Culpeper, VAPJM Oct 2016target 2023
Gas project G231, Outagamie County
Gas
60.0 MWWithdrawn / abandoned Outagamie, WIMISO May 2002target 2003
Solar project 18250, Scotland County
Solar · Masked
60.0 MWWithdrawn / abandoned Scotland, NCSoutheast Nov 2017
Solar project 200482, Richmond County
Solar
60.0 MWWithdrawn / abandoned Richmond, NCSoutheast Mar 2020
Other project G114, Juneau County
Other
60.0 MWWithdrawn / abandoned Juneau, WIMISO Aug 2001target 2006
Battery storage project GEN-2019-049, Caddo Parish County
Battery storage
60.0 MWWithdrawn / abandoned Caddo Parish, LASPP May 2019target 2027
Solar project AH1-375, Fluvanna County
Solar
60.0 MWWithdrawn / abandoned Fluvanna, VAPJM Sep 2021target 2025
Onshore wind project GEN-2016-027, Cherry County
Onshore wind
60.0 MWWithdrawn / abandoned Cherry, NESPP Mar 2016target 2017
Replace 60 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold
Other
60.0 MWWithdrawn / abandoned Linn, IAMISO Mar 2021target 2023
Solar project GI-2016-1, Pueblo County
Solar
60.0 MWWithdrawn / abandoned Pueblo, COWest Feb 2016target 2018
Other project 658, Clark County
Other · OR Solar 4, LLC
60.0 MWWithdrawn / abandoned Clark, WAWest Apr 2015target 2016
Onshore wind project G845, Cavalier County
Onshore wind
60.0 MWWithdrawn / abandoned Cavalier, NDMISO Aug 2007target 2011
Onshore wind project 7, Idaho County
Onshore wind
60.0 MWWithdrawn / abandoned Idaho, IDWest Oct 2007target 2010
Onshore wind project MPC01000, Cass County
Onshore wind
60.0 MWWithdrawn / abandoned Cass, NDMISO Mar 2008target 2008
Battery storage project 957012, Sampson County
Battery storage · Masked
60.0 MWWithdrawn / abandoned Sampson, NCSoutheast Jun 2024
Solar + storage project J2278, Edgar County
Solar + storage
60.0 MWWithdrawn / abandoned Edgar, ILMISO Mar 2022target 2025
Solar + storage project C1-41, Modoc County
Solar + storage
60.0 MWWithdrawn / abandoned Modoc, CAWest May 2021target 2023
Page 310 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)