United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR + STORAGE Β· MISOSolar + storage project J1810, White County
Solar + storage project J1810, White County is a 60.0 MW solar + storage request withdrawn in the MISO interconnection queue, in White County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedJul 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1810
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN INDIANA PUBLIC SERVICE COMPANY
- Connection point (POI)
- Reynolds 345kV to Burr Oaks 345kV
- Location
- White County, Indiana
- Technology
- Solar: 60.0 MW Β· Battery
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 20 June 2020
- Proposed online date
- September 2023
- Withdrawn
- July 2023
Location
Marker shows the centre of White County; the queue data does not give exact sites.
Other requests in White County
- Honey Creek SolarSolar + storage Β· 200 MW Β· agreement signed
- Black Prairie Solar ParkSolar Β· 200 MW Β· agreement signed
- Hoosier Line SolarSolar Β· 180 MW Β· agreement signed
- Solar project J1482, White CountySolar Β· 150 MW Β· agreement signed
- Battery storage project J2496, White CountyBattery storage Β· 400 MW Β· in study
- Battery storage project J2663, White CountyBattery storage Β· 200 MW Β· in study
- Solar project J1772, White CountySolar Β· 200 MW Β· in study
- Battery storage project J3691, White CountyBattery storage Β· 200 MW Β· in study
- Solar project J2353, White CountySolar Β· 190 MW Β· in study
- Battery storage project J3688, White CountyBattery storage Β· 150 MW Β· in study
- Battery storage project J2657, White CountyBattery storage Β· 138 MW Β· in study
- Solar project J3168, White CountySolar Β· 120 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem