🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Caden Energix Spout Spring

Caden Energix Spout Spring is a 60.0 MW solar request withdrawn in the PJM interconnection queue, in Appomattox County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2018 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE1-056
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Red House-South Creek 115 kV
Location
Appomattox County, Virginia
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
25 July 2018
Proposed online date
January 2025
Withdrawn
October 2025

Location

Marker shows the centre of Appomattox County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Appomattox County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem