BATTERY STORAGE · NYISO

Arthur Kill Energy Storage 2

Arthur Kill Energy Storage 2 is a 60.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Richmond County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedJan 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
829
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
NRG Arthur Kill Storage LLC
Connection point (POI)
Arthur Kill 138kV
Location
Richmond County, New York
Technology
Battery: 60.0 MW
Total requested
60.0 MW
Queue status
Withdrawn
Entered queue
24 April 2019
Withdrawn
January 2020

Location

Marker shows the centre of Richmond County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Richmond County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem