🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) — page 31

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 31 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Sweetbrier Hybrid Solar
Solar + storage
90.8 MWWithdrawn / abandoned Monterey, CACAISO Apr 2021target 2024
Green Borders Geothermal Phase II
Geothermal
90.0 MWWithdrawn / abandoned Churchill, NVCAISO Nov 2006target 2011
Magnolia Solar Farm
Solar
90.0 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2014
Falcon Palm Energy Center
Battery storage
90.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
High Desert Solar PV
Solar
90.0 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2014target 2018
Mallard Energy Storage Project
Battery storage
90.0 MWWithdrawn / abandoned Contra Costa, CACAISO May 2017target 2021
Kama 3 FPV
Solar + storage
87.8 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Pahrump Solar
Solar
87.5 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2020
Desert Flower Wind Farm
Onshore wind
86.4 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2023
DRY Creek (Fka Jasmin Power 3)
Gas
86.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2013target 2017
Jordan II Renewable Power Project (20/66MW)
Other
86.0 MWWithdrawn / abandoned San Diego, CACAISO Jul 2010target 2013
Ridgeview Energy Storage
Battery storage
85.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Watson Cogeneration
Gas
85.0 MWWithdrawn / abandoned Los Angeles, CACAISO May 2008target 2012
Juniper Hybrid
Solar + storage
84.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Sonora Solar Generating Station
Solar
84.0 MWWithdrawn / abandoned Imperial, CACAISO Jun 2008target 2011
Bonsall Renewable
Solar + storage
84.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2017
Heirloom Renewable
Solar + storage
84.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2017
Sagebrush Solar 1
Solar
83.3 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2020
Sanyo Ave Storage 1
Battery storage
82.6 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2023
Hydaspes
Solar + storage
82.0 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2018target 2022
Dos Amigos Solar
Solar
81.8 MWWithdrawn / abandoned Merced, CACAISO Apr 2015target 2020
Helix Storage
Battery storage
81.6 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
SEGS10 Solar
Solar
81.4 MWWithdrawn / abandoned San Bernardino, CACAISO May 2016target 2019
Bluegill Storage
Battery storage
81.4 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2025
Plaugher Ranch Solar
Solar + storage
81.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Vickers Energy Storage
Battery storage
80.0 MWWithdrawn / abandoned Los Angeles, CACAISO May 2017target 2021
Basket Ridge Solar
Solar
80.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2015target 2018
Voyager Solar Energy
Solar
80.0 MWWithdrawn / abandoned Kern, CACAISO Jul 2010target 2014
Hdla Solar
Solar
80.0 MWWithdrawn / abandoned San Bernardino, CACAISO Nov 2006target 2009
PV-31
Solar
80.0 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2008target 2013
Solcen Solar Project
Solar
80.0 MWWithdrawn / abandoned Kings, CACAISO Jul 2010target 2013
Mesa Verde Solar
Solar
80.0 MWWithdrawn / abandoned Riverside, CACAISO Nov 2011target 2015
Belridge Solar Energy 2 Project
Solar
80.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2016
Solano Solar
Solar
80.0 MWWithdrawn / abandoned Solano, CACAISO Mar 2011target 2014
Highway 58 Solar Energy Project
Solar
80.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2014
Newhall Solar Energy Project
Solar
80.0 MWWithdrawn / abandoned Fresno, CACAISO Apr 2012target 2013
KM Acquisitions
Solar
80.0 MWWithdrawn / abandoned San Bernardino, CACAISO Nov 2006target 2016
Alpine Storage
Battery storage
79.5 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2026
Windy Wash Solar
Solar
79.0 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2022
Elkhorn Expansion
Battery storage
78.6 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Coso Solar 1
Solar
78.2 MWWithdrawn / abandoned Inyo, CACAISO May 2016target 2018
Mooncrest
Battery storage
78.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Chamise
Solar + storage
77.7 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2024
Cassiopeia Solar
Solar
77.0 MWWithdrawn / abandoned Kern, CACAISO May 2017target 2021
Polvadero Hybrid Solar
Solar + storage
76.9 MWWithdrawn / abandoned Fresno, CACAISO Apr 2020target 2023
Breckenridge
Battery storage
76.5 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2025
Gonzaga Ridge Wind Farm 3
Onshore wind
76.0 MWWithdrawn / abandoned Merced, CACAISO Apr 2018target 2020
Cleanpower Solar
Solar + storage
75.4 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2018target 2020
Yuha Basin Solar
Solar
75.0 MWWithdrawn / abandoned Imperial, CACAISO Apr 2012target 2015
Riviera Solar
Solar
75.0 MWWithdrawn / abandoned Madera, CACAISO Apr 2019target 2022
Page 31 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)