Highway 58 Solar Energy Project

Highway 58 Solar Energy Project is a 80.0 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedFeb 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
786
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Windhub Substation 66kV
Location
Kern County, California
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
December 2014
Withdrawn
February 2012

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.