United States › Grid › Interconnection queues › California

SOLAR · CAISO

KM Acquisitions

KM Acquisitions is a 80.0 MW solar request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2006 (completed)
  2. Withdrawn / abandonedJan 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
142
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Kramer Substation 220kV
Location
San Bernardino County, California
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Study phase
Executed
Queue status
Withdrawn
Entered queue
6 November 2006
Proposed online date
December 2016
Withdrawn
January 2017

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem