πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

SOLAR Β· CAISO

Pahrump Solar

Pahrump Solar is a 87.5 MW solar request withdrawn in the CAISO interconnection queue, in Nye County, Nevada, connecting to VEA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJul 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1342
Grid region
CAISO (California)
Utility / transmission owner
VEA
Connection point (POI)
Vista Substation 138 kV bus.
Location
Nye County, Nevada
Technology
Solar: 87.5 MW
Total requested
87.5 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
2 May 2016
Proposed online date
December 2020
Withdrawn
July 2016

Location

Marker shows the centre of Nye County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Nye County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem