🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · CAISO

High Desert Solar PV

High Desert Solar PV is a 90.0 MW solar request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedApr 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1089
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Desert View Substation 220kV
Location
San Bernardino County, California
Technology
Solar: 90.0 MW
Total requested
90.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2014
Proposed online date
April 2018
Withdrawn
April 2015

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem