🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 304

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 304 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 338, Lake County
Solar
68.0 MWWithdrawn / abandoned Lake, TNSoutheast Jan 2018
Solar project AH1-410, Madison County
Solar
68.0 MWWithdrawn / abandoned Madison, KYPJM Sep 2021target 2024
Solar project 963467, Chester County
Solar
68.0 MWWithdrawn / abandoned Chester, SCSoutheast Sep 2024
Solar project AF1-074, Sussex County
Solar
68.0 MWWithdrawn / abandoned Sussex, VAPJM Jul 2019target 2022
Long Island City Energy Storage
Battery storage · Prologis Energy LLC
68.0 MWWithdrawn / abandoned Queens, NYNYISO Aug 2024
Onshore wind project AA1-113, Schuylkill County
Onshore wind
68.0 MWWithdrawn / abandoned Schuylkill, PAPJM Oct 2014target 2017
Solar + storage project IC-1009, Cherokee County
Solar + storage
68.0 MWWithdrawn / abandoned Cherokee, ALSoutheast Jan 2022
Solar project 430, Lake County
Solar
68.0 MWWithdrawn / abandoned Lake, TNSoutheast May 2020
Battery storage project AH1-364, Middlesex County
Battery storage
68.0 MWWithdrawn / abandoned Middlesex, VAPJM Sep 2021target 2025
Solar project AD2-216, Henry County
Solar
68.0 MWWithdrawn / abandoned Henry, VAPJM Mar 2018target 2020
Solar + storage project J2760, Hubbard County
Solar + storage
68.0 MWWithdrawn / abandoned Hubbard, MNMISO Sep 2022target 2027
Offshore wind project AH1-634, Sussex County
Offshore wind · US Wind, Inc
68.0 MWWithdrawn / abandoned Sussex, DEPJM Feb 2025target 2024
Solar
Solar
68.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Feb 2024target 2028
Solar project AH1-544, Lasalle County
Solar
67.7 MWWithdrawn / abandoned Lasalle, ILPJM Sep 2021target 2025
Hathor Solar
Solar · ABEI ENERGY & INFRASTRUCTURE
67.6 MWWithdrawn / abandoned Hunt, TXERCOT Sep 2020target 2023
Solar project GEN-2017-102, Roosevelt County
Solar
67.5 MWWithdrawn / abandoned Roosevelt, NMSPP Apr 20202020
Solar project GEN-2017-101, Hardeman County
Solar
67.5 MWWithdrawn / abandoned Hardeman, TXSPP Jul 20172020
Biomass Project
Other
67.5 MWWithdrawn / abandoned Coos, NHISO-NE Feb 2007target 2009
Onshore wind project Z2-101, Schuylkill County
Onshore wind
67.5 MWWithdrawn / abandoned Schuylkill, PAPJM Apr 2014target 2016
Waymart Wind II
Onshore wind
67.3 MWWithdrawn / abandoned Wayne, PAPJM Sep 2016target 2021
Desert Obsidian
Solar
67.2 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2020
Solar + storage project 440, Limestone County
Solar + storage
67.0 MWWithdrawn / abandoned Limestone, ALSoutheast Jun 2020
Solar project 250, Monroe County
Solar
67.0 MWWithdrawn / abandoned Monroe, MSSoutheast Jul 2014
Solar project 288, Colbert County
Solar
67.0 MWWithdrawn / abandoned Colbert, ALSoutheast Mar 2016
Nuclear project GEN-2007-030O, Washington County
Nuclear
67.0 MWWithdrawn / abandoned Washington, NESPP Jul 2007target 2012
Madera Energy Center Expansion
Gas
67.0 MWWithdrawn / abandoned Madera, CACAISO Jul 2007target 2012
Solar project 252, Monroe County
Solar
67.0 MWWithdrawn / abandoned Monroe, MSSoutheast Jul 2014
Solar project 294, Haywood County
Solar
67.0 MWWithdrawn / abandoned Haywood, TNSoutheast Jun 2016
Stockton Generation Expansion
Gas
67.0 MWWithdrawn / abandoned San Joaquin, CACAISO Jul 2007target 2014
Battery storage project AG2-314, Nicholas County
Battery storage · Deep Lake Energy Center, LLC
67.0 MWWithdrawn / abandoned Nicholas, WVPJM Mar 2021target 2024
Temple Generation I Repower
Gas
67.0 MWWithdrawn / abandoned Bell, TXERCOT Apr 2021
Solar project 289, Jackson County
Solar
67.0 MWWithdrawn / abandoned Jackson, ALSoutheast Mar 2016
Onshore wind project J2054, Freeborn County
Onshore wind
67.0 MWWithdrawn / abandoned Freeborn, MNMISO Aug 2021target 2024
Onshore wind project V4-015, Hancock County
Onshore wind
66.6 MWWithdrawn / abandoned Hancock, OHPJM Nov 2009target 2015
Onshore wind project W2-001, Hancock County
Onshore wind
66.6 MWWithdrawn / abandoned Hancock, OHPJM May 2010target 2015
Solar project AF1-307, Indiana County
Solar
66.5 MWWithdrawn / abandoned Indiana, PAPJM Sep 2019target 2023
Solar project GI-TC-2024-32, Moffat County
Solar
66.5 MWWithdrawn / abandoned Moffat, COWest May 2024target 2027
Walker Ridge Wind Energy Park
Onshore wind
66.2 MWWithdrawn / abandoned Lake, CACAISO Jul 2007target 2014
Solar project 394, Lawrence County
Solar
66.0 MWWithdrawn / abandoned Lawrence, ALSoutheast Aug 2019
Mixer Road Wind
Onshore wind · PPM Energy, Inc.
66.0 MWWithdrawn / abandoned Jefferson, NYNYISO Apr 2005
Onshore wind project GEN-2015-087, Thayer County
Onshore wind
66.0 MWWithdrawn / abandoned Thayer, NESPP Sep 20152019
Solar project 1119, San Juan County
Solar
66.0 MWWithdrawn / abandoned San Juan, UTWest Mar 2019target 2021
Solar project AH1-553, Madison County
Solar
66.0 MWWithdrawn / abandoned Madison, OHPJM Sep 2021target 2025
Solar project 315, Monroe County
Solar
66.0 MWWithdrawn / abandoned Monroe, MSSoutheast May 2017
Solar project 391, Tallahatchie County
Solar
66.0 MWWithdrawn / abandoned Tallahatchie, MSSoutheast Jun 2019
Solar project 273, Lawrence County
Solar
66.0 MWWithdrawn / abandoned Lawrence, ALSoutheast Sep 2015
Solar project 345, Shelby County
Solar
66.0 MWWithdrawn / abandoned Shelby, TNSoutheast Apr 2018
Solar project 726, Crook County
Solar
66.0 MWWithdrawn / abandoned Crook, ORWest Jan 2016target 2018
Solar project 281, Benton County
Solar
66.0 MWWithdrawn / abandoned Benton, TNSoutheast Feb 2016
Mahogany Storage
Battery storage
66.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Page 304 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)