ONSHORE WIND · NYISO

Mixer Road Wind

Mixer Road Wind is a 66.0 MW onshore wind request withdrawn in the NYISO interconnection queue, in Jefferson County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2005 (completed)
  2. Withdrawn / abandonedOct 2006 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
190
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
PPM Energy, Inc.
Connection point (POI)
West Adams 115kV
Location
Jefferson County, New York
Technology
Wind: 66.0 MW
Total requested
66.0 MW
Queue status
Withdrawn
Entered queue
8 April 2005
Withdrawn
October 2006

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Jefferson County