Madera Energy Center Expansion

Madera Energy Center Expansion is a 67.0 MW gas request withdrawn in the CAISO interconnection queue, in Madera County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2007 (completed)
  2. Withdrawn / abandonedApr 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
247
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Borden Substation 230kV Bus
Location
Madera County, California
Technology
Gas: 67.0 MW
Total requested
67.0 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 July 2007
Proposed online date
April 2012
Withdrawn
April 2011

Location

Marker shows the centre of Madera County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Madera County