United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2018 requests) โ page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Juno Storage Other ยท Intersect Power |
495 MW | Withdrawn / abandoned |
| Ponta Power Plant Gas ยท Pro Energy Services LLC |
484 MW | Withdrawn / abandoned |
| Gas project AD2-182, Marshall County Gas |
482 MW | Withdrawn / abandoned |
| Nuclear project TCS-11, Butte County Nuclear |
462 MW | Withdrawn / abandoned |
| Offshore wind project AE2-023, Atlantic County Offshore wind |
445 MW | Withdrawn / abandoned |
| Offshore wind project AE2-025, Ocean County Offshore wind |
445 MW | Withdrawn / abandoned |
| NY Wind Canal Onshore wind ยท Bay State Wind LLC |
440 MW | Withdrawn / abandoned |
| Onshore wind project J1106, Redwood County Onshore wind |
414 MW | Withdrawn / abandoned |
| South Bend Generating Station Gas |
410 MW | Withdrawn / abandoned |
| Sageberry Solar Solar + storage |
404 MW | Withdrawn / abandoned |
| Onshore wind project G0581, Morrow County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-10, Banner County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-7, Banner County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-12, Banner County Onshore wind |
401 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-8, Banner County Onshore wind |
401 MW | Withdrawn / abandoned |
| Solar project GEN-2018-066, Lancaster County Solar |
400 MW | Withdrawn / abandoned |
| Solar project 1029, Lake County Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Company JL, Humboldt County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar project GEN-2018-092, Foard County Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q64, Beaver County Solar + storage ยท Intermountain Power Agency |
400 MW | Withdrawn / abandoned |
| Solar project J1010, Kenosha County Solar |
400 MW | Withdrawn / abandoned |
| Solar project J1009, Kenosha County Solar |
400 MW | Withdrawn / abandoned |
| Onshore wind project J960, Presque Isle County Onshore wind |
400 MW | Withdrawn / abandoned |
| Solar + storage project 1070, Utah County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar project J1011, Kenosha County Solar |
400 MW | Withdrawn / abandoned |
| Solar project AE1-069, Greensville County Solar |
400 MW | Withdrawn / abandoned |
| Onshore wind project J966, Putnam County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project J1082, Grundy County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2018-041, Ralls County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2018-119, Johnson County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2018-046, Banner County Onshore wind |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q11, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar project IA-PNM-2018-06, Bernalillo County Solar |
400 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
400 MW | Withdrawn / abandoned |
| Spectrum Solar Solar ยท IP Spectrum, LLC |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q65, Clark County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Company JJ, Lander County Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project G0607, Klamath County Battery storage |
394 MW | Withdrawn / abandoned |
| Onshore wind project 535, Jerome County Onshore wind |
375 MW | Withdrawn / abandoned |
| Onshore wind project J1043, Montcalm County Onshore wind |
374 MW | Withdrawn / abandoned |
| Onshore wind project AD2-136, Seneca County Onshore wind |
360 MW | Withdrawn / abandoned |
| Solar + storage project AE1-198, Mchenry County Solar + storage |
357 MW | Withdrawn / abandoned |
| Black Angus Onshore wind ยท Apex Clean |
353 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
352 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-14, Banner County Onshore wind |
350 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-13, Banner County Onshore wind |
350 MW | Withdrawn / abandoned |
| Solar project Company IY, Pershing County Solar |
350 MW | Withdrawn / abandoned |
| Solar project IC-712, Calhoun County Solar |
350 MW | Withdrawn / abandoned |
| Onshore wind project J1075, Cass County Onshore wind |
350 MW | Withdrawn / abandoned |
| Solar + storage project Company ID, Lander County Solar + storage |
350 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)306 ยท 50.5 GW
- PJM (Mid-Atlantic, Midwest)311 ยท 46.6 GW
- MISO (Midcontinent)165 ยท 28.2 GW
- Southeast (non-ISO utilities)248 ยท 28.2 GW
- CAISO (California)67 ยท 21.7 GW
- SPP (Southwest Power Pool)92 ยท 16.8 GW
- ERCOT (Texas)77 ยท 15.0 GW
- NYISO (New York)74 ยท 11.2 GW
- ISO-NE (New England)84 ยท 8,151 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)