Solar + storage project Company JJ, Lander County

Solar + storage project Company JJ, Lander County is a 400 MW solar + storage request withdrawn in the West interconnection queue, in Lander County, Nevada, connecting to NV Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Company JJ
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Lander County, Nevada
Technology
Solar: 400 MW Β· Battery
Total requested
400 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
28 September 2018
Proposed online date
June 2021

Location

Marker shows the centre of Lander County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Lander County