United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2015 requests) โ page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project 2015-G1 Solar |
250 MW | Withdrawn / abandoned |
| Onshore wind project AA2-075, Van Wert County Onshore wind |
250 MW | Withdrawn / abandoned |
| Fresno Solar 1 Solar |
247 MW | Withdrawn / abandoned |
| Wind Onshore wind |
245 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2015-101, Deaf Smith County Onshore wind |
240 MW | Withdrawn / abandoned |
| Combustion Turbine Generator Gas |
238 MW | Withdrawn / abandoned |
| Gas project J444, Wayne County Gas |
235 MW | Withdrawn / abandoned |
| Linden Cogen Uprate Gas ยท East Coast Power LLC |
234 MW | Withdrawn / abandoned |
| Gas project AA2-183, Union County Gas |
234 MW | Withdrawn / abandoned |
| Combustion Turbine (Alt to Q523) Gas |
234 MW | Withdrawn / abandoned |
| Combustion Turbine Gas |
227 MW | Withdrawn / abandoned |
| Gas project AA2-077, Philadelphia County Gas |
220 MW | Withdrawn / abandoned |
| Wind Onshore wind |
216 MW | Withdrawn / abandoned |
| Gas project AA2-050, Philadelphia County Gas |
210 MW | Withdrawn / abandoned |
| Gas project 43, Pima County Gas |
206 MW | Withdrawn / abandoned |
| Algoso Es Battery storage |
206 MW | Withdrawn / abandoned |
| Mikado Solar + storage |
206 MW | Withdrawn / abandoned |
| Solar project 710, Kane County Solar |
204 MW | Withdrawn / abandoned |
| Onshore wind project J448, Mitchell County Onshore wind |
202 MW | Withdrawn / abandoned |
| Onshore wind project GI-51, Dekalb County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2015-030, Noble County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J528, Adair County Onshore wind |
200 MW | Withdrawn / abandoned |
| Dawn Wind Ranch Onshore wind ยท Cielo |
200 MW | Withdrawn / abandoned |
| Hecate McCamey A Solar Solar ยท Hecate Energy |
200 MW | Withdrawn / abandoned |
| Mount Vernon Solar Solar |
200 MW | Withdrawn / abandoned |
| North Slope Wind Onshore wind ยท EDP Renewables North America |
200 MW | Withdrawn / abandoned |
| Onshore wind project J519, Audubon County Onshore wind |
200 MW | Withdrawn / abandoned |
| Ancho Creek Solar Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2015-086, Woodward County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2015-049, Dewey County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project J464, St. Tammany Parish County Solar |
200 MW | Withdrawn / abandoned |
| Tecovas 1 W Onshore wind ยท Engie |
200 MW | Withdrawn / abandoned |
| CA200S PV Project Solar |
200 MW | Withdrawn / abandoned |
| Tecovas 2 W Onshore wind ยท Engie |
200 MW | Withdrawn / abandoned |
| Palomas Solar Project Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project J537, Sanilac County Onshore wind |
200 MW | Withdrawn / abandoned |
| Salt Fork 2 Wind Onshore wind ยท Cielo |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2015-003, Grant County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J458, Clark County Onshore wind |
200 MW | Withdrawn / abandoned |
| Otay Mesa BESS Battery storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2015-071, Beckham County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project J463, Montgomery County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project J450, Huron County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J459, Grant County Onshore wind |
200 MW | Withdrawn / abandoned |
| Mustang Draw Solar Solar ยท Lincoln Clean |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2015-061, Logan County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project 644, Navajo County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project GEN-2015-002, Canadian County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project J531, Chickasaw County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J511, Oliver County Onshore wind |
200 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)231 ยท 27.2 GW
- MISO (Midcontinent)53 ยท 17.2 GW
- CAISO (California)91 ยท 12.3 GW
- SPP (Southwest Power Pool)72 ยท 11.1 GW
- ISO-NE (New England)46 ยท 7,500 MW
- West (non-ISO utilities)197 ยท 6,025 MW
- ERCOT (Texas)28 ยท 5,278 MW
- Southeast (non-ISO utilities)49 ยท 4,719 MW
- NYISO (New York)33 ยท 4,251 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)