ONSHORE WIND Β· ERCOT

Salt Fork 2 Wind

Salt Fork 2 Wind is a 200 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedAug 2015 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
16INR0082
Grid region
ERCOT (Texas)
Developer
Cielo
Connection point (POI)
79000 Gray 345kV
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
13 February 2015
Agreement signed
18 August 2015
Proposed online date
August 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in