United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Queue requests in study in the USA (2022 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,272255.2 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,272 requests ยท page 3 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Tempesta
Solar
443 MWPaused / redesign Kaufman, TXERCOT Jun 2022
Replacing 300 MW of existing coal generation with BESS; Edgewater 5
Other
423 MWIn study MISO Feb 2022target 2025
Solar + storage project IC-1059, Pike County
Solar + storage
420 MWPaused / redesign Pike, ALSoutheast Sep 2022target 2027
Wind + storage project G0728, Sherman County
Wind + storage
420 MWIn study Sherman, ORWest Feb 2022target 2026
Battery storage project AH2-333, Salem County
Battery storage
415 MWIn study Salem, NJPJM Mar 2022target 2025
Smith Lake Solar DC
Solar + storage ยท Smith Lake Solar
402 MWIn study Grimes, TXERCOT Feb 2022target 2028
Bottom Grass Solar II
Solar + storage ยท Flint Rock Solar Project, LLC
402 MWIn study Colorado, TXERCOT Nov 2022target 2028
Battery storage project Company 212, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Battery storage project J2496, White County
Battery storage
400 MWIn study White, INMISO Sep 2022target 2026
Solar + storage project 2023-G1
Solar + storage
400 MWIn study West Oct 2022target 2025
Solar + storage project G0744, Grant County
Solar + storage
400 MWIn study Grant, WAWest May 2022target 2026
Solar project J2088, Lee County
Solar
400 MWIn study Lee, ARMISO Jul 2022target 2027
Battery storage project IC-1102, Montgomery County
Battery storage
400 MWPaused / redesign Montgomery, ALSoutheast Dec 2022target 2026
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Wind + storage project Company MX, Lyon County
Wind + storage
400 MWPaused / redesign Lyon, NVWest Mar 2022target 2027
Solar project J2931, Henderson County
Solar
400 MWIn study Henderson, KYMISO Sep 2022target 2025
Solar + storage project J2907, Grant County
Solar + storage
400 MWIn study Grant, ARMISO Sep 2022target 2026
Solar + storage project Q486, Coconino County
Solar + storage
400 MWIn study Coconino, AZWest Sep 2022target 2027
Solar project J2396, Calhoun County
Solar
400 MWIn study Calhoun, ARMISO Sep 2022target 2025
Solar + storage project C2-203, Klamath County
Solar + storage
400 MWIn study Klamath, ORWest May 2022target 2025
Solar project AH2-352
Solar
400 MWIn study INPJM Mar 2022target 2026
Solar + storage project 667, Elmore County
Solar + storage ยท Martha Fields Energy Center, LLC
400 MWPaused / redesign Elmore, IDWest Aug 2022target 2029
Battery storage project Company 226, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Wind + storage project J3015, Iroquois County
Wind + storage
400 MWIn study Iroquois, ILMISO Sep 2022target 2027
Surplus; G876/G877
Wind + storage
400 MWIn study Mclean, ILMISO Sep 2022target 2025
Solar + storage project G0732, Benton County
Solar + storage
400 MWIn study Benton, WAWest Mar 2022target 2027
Solar project AH2-257, Vermillion County
Solar
400 MWIn study Vermillion, INPJM Mar 2022target 2024
Solar + storage project G0747, Klamath County
Solar + storage
400 MWIn study Klamath, ORWest Jun 2022target 2026
Solar + storage project Q480, Navajo County
Solar + storage
400 MWIn study Navajo, AZWest Sep 2022target 2025
Solar + storage project G0820, Douglas County
Solar + storage
400 MWIn study Douglas, WAWest Nov 2022target 2027
Solar project J2107, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Solar project J2099, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Solar project J2185, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Battery storage project Company 228, Clark County
Battery storage
380 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Solar project J2866, Nevada County
Solar
375 MWIn study Nevada, ARMISO Sep 2022target 2027
Solar project J2865, Ouachita County
Solar
375 MWIn study Ouachita, ARMISO Sep 2022target 2027
Solar project J2864, Nevada County
Solar
375 MWIn study Nevada, ARMISO Sep 2022target 2027
Earthwise Solar
Solar ยท Quanah Solar 2
371 MWIn study Hardeman, TXERCOT Mar 2022target 2026
Solar project J3040, Ouachita County
Solar
365 MWIn study Ouachita, ARMISO Sep 2022target 2027
Solar + storage project AH2-413, Huntington County
Solar + storage
365 MWIn study Huntington, INPJM Mar 2022target 2026
Sombrero Solar
Solar ยท Aurora Solar LLC
352 MWIn study Schleicher, TXERCOT Mar 2022target 2028
Solar + storage project J2390, Fulton County
Solar + storage
350 MWIn study Fulton, ILMISO Sep 2022target 2026
Gas project J2944, Portage County
Gas
350 MWIn study Portage, WIMISO Sep 2022target 2027
Solar + storage project Company NB, White Pine County
Solar + storage
350 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar project AH2-340, Stark County
Solar
350 MWIn study Stark, ILPJM Mar 2022target 2027
Battery storage project AH2-414, Huntington County
Battery storage
350 MWIn study Huntington, INPJM Mar 2022target 2026
Gas project J2945, Washington County
Gas
350 MWIn study Washington, IAMISO Sep 2022target 2027
Solar project J3209, Rapides Parish County
Solar
350 MWIn study Rapides Parish, LAMISO Sep 2022target 2026
Solar + storage project Company OA, Humboldt County
Solar + storage
350 MWPaused / redesign Humboldt, NVWest Sep 2022target 2030
HyFuels Green Lake Solar
Solar ยท HyFuels Green Lake Solar LLC
347 MWIn study Victoria, TXERCOT Sep 2022target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)