Solar project J2866, Nevada County

Solar project J2866, Nevada County is a 375 MW solar request in interconnection study in the MISO interconnection queue, in Nevada County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2866
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
McNeil 500kV (A) to Etta 500kV (B)
Location
Nevada County, Arkansas
Technology
Solar: 375 MW
Total requested
375 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
13 September 2022
Proposed online date
August 2027

Location

Marker shows the centre of Nevada County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in Nevada County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem