SOLAR · MISOSolar project J2866, Nevada County
Solar project J2866, Nevada County is a 375 MW solar request in interconnection study in the MISO interconnection queue, in Nevada County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2866
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- McNeil 500kV (A) to Etta 500kV (B)
- Location
- Nevada County, Arkansas
- Technology
- Solar: 375 MW
- Total requested
- 375 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 13 September 2022
- Proposed online date
- August 2027
Location
Marker shows the centre of Nevada County; the queue data does not give exact sites.
Other requests in Nevada County
- Solar project J2864, Nevada CountySolar · 375 MW · in study
- Solar + storage project J4139, Nevada CountySolar + storage · 115 MW · in study
- Solar project J2240, Nevada CountySolar · 120 MW · withdrawn
- Solar project J2638, Nevada CountySolar · 58.0 MW · withdrawn
- Solar project J3218, Nevada CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem