United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
SOLAR Β· MISOSolar project J3218, Nevada County
Solar project J3218, Nevada County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Nevada County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3218
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- Prescott (#337507) to Emmett (#337505)
- Location
- Nevada County, Arkansas
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 September 2022
- Proposed online date
- June 2025
- Withdrawn
- July 2025
Location
Marker shows the centre of Nevada County; the queue data does not give exact sites.
Other requests in Nevada County
- Solar project J2866, Nevada CountySolar Β· 375 MW Β· in study
- Solar project J2864, Nevada CountySolar Β· 375 MW Β· in study
- Solar + storage project J4139, Nevada CountySolar + storage Β· 115 MW Β· in study
- Solar project J2240, Nevada CountySolar Β· 120 MW Β· withdrawn
- Solar project J2638, Nevada CountySolar Β· 58.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem