United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· MISO

Solar project J2240, Nevada County

Solar project J2240, Nevada County is a 120 MW solar request withdrawn in the MISO interconnection queue, in Nevada County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2240
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Prescott 337507 to Emmett 337505
Location
Nevada County, Arkansas
Technology
Solar: 120 MW
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
21 December 2021
Proposed online date
February 2024
Withdrawn
March 2025

Location

Marker shows the centre of Nevada County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Nevada County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem