Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown12626.5 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

126 requests Β· page 3 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 236, Gadsden County
Solar Β· Florida Renewable Partners, LLC
74.5 MWIn study Gadsden, FLSoutheast Jul 2018target 2021
Solar project 357, Brevard County
Solar Β· FPL
74.5 MWIn study Brevard, FLSoutheast Jul 2018target 2028
Solar project 109, Horry County
Solar
64.0 MWIn study Horry, SCSoutheast Jul 2018target 2020
Prospect Energy Storage
Battery storage
58.8 MWPaused / redesign Sacramento, CACAISO Apr 2018target 2028
R Massengale
Gas
58.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Battery storage project Q289, Maricopa County
Battery storage
50.0 MWIn study Maricopa, AZWest Sep 2018target 2023
Broomstick Solar Energy Centergy Center
Solar
50.0 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Hardin Energy Center β€šΓ„Γ¬ Storage I
Battery storage
50.0 MWPaused / redesign Hardin, OHPJM Mar 2018target 2025
Cadence Energy Storage
Battery storage
50.0 MWPaused / redesign Union, OHPJM Mar 2018target 2026
Recreation Solar
Solar
49.5 MWPaused / redesign Guernsey, OHPJM Sep 2018target 2025
Concho Solar I
Solar
49.0 MWPaused / redesign Queen Anne's, MDPJM Mar 2018target 2024
Vinton Energy Storage
Battery storage
42.0 MWPaused / redesign Vinton, OHPJM Aug 2018target 2026
Ho-Fel Solar
Solar
40.0 MWPaused / redesign Isle Of Wight, VAPJM Sep 2018target 2026
SP TX-12B Phase III
Solar Β· ConEd Development
40.0 MWIn study Upton, TXERCOT Sep 2018target 2025
Half Moon Battery
Battery storage
30.2 MWPaused / redesign Hidalgo, TXERCOT Sep 2018
Blue Creek Wind Farm
Solar
26.0 MWPaused / redesign Van Wert, OHPJM Sep 2018target 2024
Brandon
Gas
21.0 MWPaused / redesign Lubbock, TXERCOT Sep 2018target 2021
Solar + storage project 340, Yellowstone County
Solar + storage
20.0 MWIn study Yellowstone, MTWest Mar 2018target 2021
Ticonderoga Solar
Solar Β· ELP Ticonderoga Solar LLC
20.0 MWIn study Essex, NYNYISO Jun 2018target 2026
Confer Solar I
Solar
20.0 MWPaused / redesign Centre, PAPJM Oct 2018target 2026
Magruder BESS
Battery storage Β· Mitchell Energy Facility, LLC
20.0 MWIn study Ulster, NYNYISO Jul 2018target 2028
Solar + storage project 80, Spokane County
Solar + storage
19.0 MWIn study Spokane, WAWest Dec 2018target 2025
Blue Summit repower
Onshore wind
9.9 MWPaused / redesign Wilbarger, TXERCOT Jan 2018
Milpa Power Bank
Battery storage
3.0 MWIn study Santa Clara, CACAISO Apr 2018target 2025
Battery storage project 70, Spokane County
Battery storage
2.5 MWIn study Spokane, WAWest Aug 2018target 2019
Solar project 71, Lincoln County
Solar
1.0 MWIn study Lincoln, WAWest Oct 2018target 2020
Page 3 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)