OCTARY USA Β· INTERCONNECTION QUEUESQueue requests in study in the USA (2018 requests) β page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project 236, Gadsden County Solar Β· Florida Renewable Partners, LLC |
74.5 MW | In study |
| Solar project 357, Brevard County Solar Β· FPL |
74.5 MW | In study |
| Solar project 109, Horry County Solar |
64.0 MW | In study |
| Prospect Energy Storage Battery storage |
58.8 MW | Paused / redesign |
| R Massengale Gas |
58.0 MW | Paused / redesign |
| Battery storage project Q289, Maricopa County Battery storage |
50.0 MW | In study |
| Broomstick Solar Energy Centergy Center Solar |
50.0 MW | Paused / redesign |
| Hardin Energy Center βΓΓ¬ Storage I Battery storage |
50.0 MW | Paused / redesign |
| Cadence Energy Storage Battery storage |
50.0 MW | Paused / redesign |
| Recreation Solar Solar |
49.5 MW | Paused / redesign |
| Concho Solar I Solar |
49.0 MW | Paused / redesign |
| Vinton Energy Storage Battery storage |
42.0 MW | Paused / redesign |
| Ho-Fel Solar Solar |
40.0 MW | Paused / redesign |
| SP TX-12B Phase III Solar Β· ConEd Development |
40.0 MW | In study |
| Half Moon Battery Battery storage |
30.2 MW | Paused / redesign |
| Blue Creek Wind Farm Solar |
26.0 MW | Paused / redesign |
| Brandon Gas |
21.0 MW | Paused / redesign |
| Solar + storage project 340, Yellowstone County Solar + storage |
20.0 MW | In study |
| Ticonderoga Solar Solar Β· ELP Ticonderoga Solar LLC |
20.0 MW | In study |
| Confer Solar I Solar |
20.0 MW | Paused / redesign |
| Magruder BESS Battery storage Β· Mitchell Energy Facility, LLC |
20.0 MW | In study |
| Solar + storage project 80, Spokane County Solar + storage |
19.0 MW | In study |
| Blue Summit repower Onshore wind |
9.9 MW | Paused / redesign |
| Milpa Power Bank Battery storage |
3.0 MW | In study |
| Battery storage project 70, Spokane County Battery storage |
2.5 MW | In study |
| Solar project 71, Lincoln County Solar |
1.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)40 Β· 10.2 GW
- PJM (Mid-Atlantic, Midwest)34 Β· 5,884 MW
- NYISO (New York)15 Β· 3,444 MW
- ERCOT (Texas)16 Β· 2,703 MW
- Southeast (non-ISO utilities)13 Β· 1,590 MW
- CAISO (California)4 Β· 1,302 MW
- ISO-NE (New England)1 Β· 827 MW
- SPP (Southwest Power Pool)3 Β· 500 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)