Prospect Energy Storage

Prospect Energy Storage is a 58.8 MW battery storage request suspended in the CAISO interconnection queue, in Sacramento County, California, connecting to PGAE.

Queue statusPaused / redesign
  1. PlanningQueued Apr 2018 (current stage)
  2. ConsentedJul 2020 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1507
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Gold Hill 60 kV
Location
Sacramento County, California
Technology
Battery: 58.8 MW
Total requested
58.8 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Suspended
Entered queue
16 April 2018
Agreement signed
10 July 2020
Proposed online date
June 2028

Location

Marker shows the centre of Sacramento County; the queue data does not give exact sites.