United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Illinois — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown35863.7 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

358 requests · page 3 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2403, Johnson County
Solar
200 MWIn study Johnson, ILMISO Sep 2022target 2025
Battery storage project J4199, Fulton County
Battery storage
200 MWIn study Fulton, ILMISO Sep 2025target 2029
Battery storage project J3031, Jefferson County
Battery storage
200 MWIn study Jefferson, ILMISO Sep 2022target 2026
Onshore wind project J2049, Shelby County
Onshore wind
200 MWIn study Shelby, ILMISO Mar 2022target 2025
Battery storage project J2402, Johnson County
Battery storage
200 MWIn study Johnson, ILMISO Sep 2022target 2025
Battery storage project J3296, Hamilton County
Battery storage
200 MWIn study Hamilton, ILMISO Apr 2024target 2027
Onshore wind project J1831, Menard County
Onshore wind
200 MWIn study Menard, ILMISO Jun 2020target 2026
Solar project J3944, Bureau County
Solar
200 MWIn study Bureau, ILMISO Feb 2025target 2030
Solar project J3880, Clay County
Solar
200 MWIn study Clay, ILMISO Feb 2025target 2030
Onshore wind project J1701, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Dec 2021target 2026
Onshore wind project J2614, Henry County
Onshore wind
200 MWIn study Henry, ILMISO Sep 2022target 2026
Battery storage project J3497, Pulaski County
Battery storage
200 MWIn study Pulaski, ILMISO Apr 2024target 2028
Solar + storage project J3080, Pulaski County
Solar + storage
200 MWIn study Pulaski, ILMISO Sep 2022target 2025
Solar + storage project AH2-363, Kankakee County
Solar + storage
200 MWIn study Kankakee, ILPJM Mar 2022target 2027
Solar project AH1-151, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2025
Onshore wind project J1926, Tazewell County
Onshore wind
200 MWIn study Tazewell, ILMISO Mar 2022target 2025
Onshore wind project J3338, Hamilton County
Onshore wind
200 MWIn study Hamilton, ILMISO Apr 2024target 2028
Battery storage project J2587, Edgar County
Battery storage
200 MWIn study Edgar, ILMISO Sep 2022target 2025
Solar project AH1-150, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2025
Onshore wind project J3493, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Apr 2024target 2028
Solar project J3811, Clay County
Solar
200 MWIn study Clay, ILMISO Apr 2024target 2028
Battery storage project J3881, Clay County
Battery storage
200 MWIn study Clay, ILMISO Feb 2025target 2030
Battery storage project J3660, Rock Island County
Battery storage
200 MWIn study Rock Island, ILMISO Apr 2024target 2028
Steward Creek Solar
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Mar 2020target 2023
Solar project J3256, Clark County
Solar
200 MWIn study Clark, ILMISO Apr 2024target 2028
Surplus; J1712
Battery storage
200 MWIn study Perry, ILMISO Apr 2025target 2027
Battery storage project J2607, Montgomery County
Battery storage
200 MWIn study Montgomery, ILMISO Sep 2022target 2026
Solar project J3095, Ford County
Solar
200 MWIn study Ford, ILMISO Sep 2022target 2025
South Dixon Solar
Solar · Deriva Energy Solar, LLC
200 MWIn study Lee, ILPJM Sep 2019target 2022
Solar + storage project J2388, Macon County
Solar + storage
200 MWIn study Macon, ILMISO Sep 2022target 2026
Solar project J3847, Jefferson County
Solar
200 MWIn study Jefferson, ILMISO Jan 2025target 2029
Battery storage project J4002, Edgar County
Battery storage
200 MWIn study Edgar, ILMISO Apr 2025target 2030
Onshore wind project J2938, Knox County
Onshore wind
200 MWIn study Knox, ILMISO Sep 2022target 2025
Battery storage project J2998, St. Clair County
Battery storage
200 MWIn study St. Clair, ILMISO Sep 2022target 2025
Onshore wind project AI1-191, Stephenson County
Onshore wind
200 MWIn study Stephenson, ILPJM Sep 2022target 2027
Battery storage project J3298, Tazewell County
Battery storage
200 MWIn study Tazewell, ILMISO Apr 2024target 2027
Solar project AG2-364, Tazewell County
Solar · Mackinaw Solar LLC
200 MWIn study Tazewell, ILPJM Mar 2025target 2024
Battery storage project J3729, Franklin County
Battery storage
200 MWIn study Franklin, ILMISO Apr 2024target 2028
Battery storage project J2379, Clay County
Battery storage
200 MWIn study Clay, ILMISO Sep 2022target 2026
Riverbank Energy
Battery storage · Lincoln Reserve Energy, LLC
200 MWIn study Cook, ILPJM Mar 2020target 2024
Battery storage project J2532, Sangamon County
Battery storage
200 MWIn study Sangamon, ILMISO Sep 2022target 2026
Battery storage project AI1-023, Mclean County
Battery storage
200 MWIn study Mclean, ILPJM Apr 2022target 2026
Solar project J2033, Clay County
Solar
200 MWIn study Clay, ILMISO Aug 2021target 2024
Battery storage project J4137, Pulaski County
Battery storage
200 MWIn study Pulaski, ILMISO Sep 2025target 2030
Onshore wind project J2963, Mason County
Onshore wind
200 MWIn study Mason, ILMISO Sep 2022target 2025
Battery storage project J3947, Shelby County
Battery storage
200 MWIn study Shelby, ILMISO Mar 2025target 2030
Battery storage project AG2-544, Mchenry County
Battery storage · Monarch Grid, LLC
200 MWIn study Mchenry, ILPJM Mar 2025target 2024
Solar project AH1-044, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2024
Solar project J4003, Edgar County
Solar
200 MWIn study Edgar, ILMISO Apr 2025target 2030
Lower Crossing Wind
Onshore wind
200 MWPaused / redesign Kankakee, ILPJM Jan 2018target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)