Battery storage project J2587, Edgar County

Battery storage project J2587, Edgar County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Edgar County, Illinois, connecting to DUKE ENERGY INDIANA.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2587
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Sugar Creek - Cayuga CT 345.0kV
Location
Edgar County, Illinois
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 September 2022
Proposed online date
April 2025

Location

Marker shows the centre of Edgar County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Edgar County