United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

ONSHORE WIND Β· MISO

Onshore wind project G979, Edgar County

Onshore wind project G979, Edgar County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Edgar County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2009 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. ConsentedJun 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G979
Grid region
MISO (Midcontinent)
Connection point (POI)
Sydney - Kansas 345 kV
Location
Edgar County, Illinois
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
6 March 2009
Agreement signed
7 June 2011
Proposed online date
August 2010
Withdrawn
June 2011

Location

Marker shows the centre of Edgar County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Edgar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem