United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 27

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 27 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1687, Decatur County
Solar
160 MWWithdrawn / abandoned Decatur, INMISO Dec 2021target 2026
Solar project J1356, Martin County
Solar
160 MWWithdrawn / abandoned Martin, INMISO Apr 2019target 2023
Solar project J1225, Washington County
Solar
160 MWWithdrawn / abandoned Washington, ILMISO Apr 2019target 2023
Solar + storage project J3775, Desha County
Solar + storage
160 MWWithdrawn / abandoned Desha, ARMISO Apr 2024target 2028
Solar project J2928, Poinsett County
Solar
160 MWWithdrawn / abandoned Poinsett, ARMISO Sep 2022target 2026
Onshore wind project H031, Wilkin County
Onshore wind
160 MWWithdrawn / abandoned Wilkin, MNMISO May 2008target 2012
Other project G302, Green Lake County
Other
160 MWWithdrawn / abandoned Green Lake, WIMISO Feb 2003target 2003
Solar project J3589, Lincoln County
Solar
160 MWWithdrawn / abandoned Lincoln, MSMISO Apr 2024target 2028
Solar project J3429, Pemiscot County
Solar
160 MWWithdrawn / abandoned Pemiscot, MOMISO Apr 2024target 2028
Solar project J1582, St. Croix County
Solar
160 MWWithdrawn / abandoned St. Croix, WIMISO Feb 2022target 2024
Onshore wind project G376, Green Lake County
Onshore wind
160 MWWithdrawn / abandoned Green Lake, WIMISO Nov 2003target 2006
Solar project J3127, Monroe County
Solar
160 MWWithdrawn / abandoned Monroe, ARMISO Sep 2022target 2026
Other project J3437, Ogemaw County
Other
160 MWWithdrawn / abandoned Ogemaw, MIMISO May 2024target 2027
Other project G079, Vermillion County
Other
160 MWWithdrawn / abandoned Vermillion, INMISO Feb 2001target 2002
Onshore wind project G335, Fond Du Lac County
Onshore wind
160 MWWithdrawn / abandoned Fond Du Lac, WIMISO Apr 2003target 2005
Battery storage project J2992, Perry County
Battery storage
160 MWWithdrawn / abandoned Perry, MSMISO Sep 2022target 2025
Onshore wind project MPC01400, Polk County
Onshore wind
160 MWWithdrawn / abandoned Polk, MNMISO May 2008target 2011
Solar project J1970, Champaign County
Solar
160 MWWithdrawn / abandoned Champaign, ILMISO Mar 2022target 2025
Solar project J1974, Coles County
Solar
160 MWWithdrawn / abandoned Coles, ILMISO Mar 2022target 2025
Solar project J4036, Cross County
Solar
160 MWWithdrawn / abandoned Cross, ARMISO Jul 2025target 2029
Solar project J3877, Pike County
Solar
160 MWWithdrawn / abandoned Pike, INMISO Jan 2025target 2029
Solar project J2366, Portage County
Solar
160 MWWithdrawn / abandoned Portage, WIMISO Sep 2022target 2030
Solar + storage project J2398, Craighead County
Solar + storage
160 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2025
Onshore wind project G721, Otter Tail County
Onshore wind
160 MWWithdrawn / abandoned Otter Tail, MNMISO Dec 2006target 2012
Solar + storage project J3812, Phillips County
Solar + storage
159 MWWithdrawn / abandoned Phillips, ARMISO Apr 2024target 2028
Onshore wind project G504, Sanilac County
Onshore wind
158 MWWithdrawn / abandoned Sanilac, MIMISO Mar 2005target 2005
Solar project J4033, Christian County
Solar
157 MWWithdrawn / abandoned Christian, ILMISO Jun 2025target 2030
Solar project J3624, Columbia County
Solar
155 MWWithdrawn / abandoned Columbia, ARMISO Apr 2024target 2028
Solar project J3380, Cleveland County
Solar
155 MWWithdrawn / abandoned Cleveland, ARMISO Apr 2024target 2028
Solar project J3238, Evangeline Parish County
Solar
155 MWWithdrawn / abandoned Evangeline Parish, LAMISO Apr 2024target 2028
Solar project J3741, Cleveland County
Solar
155 MWWithdrawn / abandoned Cleveland, ARMISO Apr 2024target 2028
Solar project MPC04200, Clearwater County
Solar
154 MWWithdrawn / abandoned Clearwater, MNMISO Nov 2020target 2024
Onshore wind project J3029, Freeborn County
Onshore wind
153 MWWithdrawn / abandoned Freeborn, MNMISO Sep 2022target 2026
Gas project J397, Marquette County
Gas
153 MWWithdrawn / abandoned Marquette, MIMISO Sep 2014target 2016
Onshore wind project J489, Grant County
Onshore wind
152 MWWithdrawn / abandoned Grant, SDMISO Nov 2015target 2018
Onshore wind project J496, Sanilac County
Onshore wind
152 MWWithdrawn / abandoned Sanilac, MIMISO Nov 2015target 2017
Onshore wind project J651, Grant County
Onshore wind
152 MWWithdrawn / abandoned Grant, SDMISO Jun 2016target 2018
Onshore wind project J1187, Mercer County
Onshore wind
152 MWWithdrawn / abandoned Mercer, NDMISO Mar 2018target 2022
Onshore wind project MPC02800, Cass County
Onshore wind
152 MWWithdrawn / abandoned Cass, NDMISO May 2016target 2017
Onshore wind project J828, Montgomery County
Onshore wind
152 MWWithdrawn / abandoned Montgomery, INMISO Jun 2017target 2020
Onshore wind project J650, Grant County
Onshore wind
152 MWWithdrawn / abandoned Grant, SDMISO Jun 2016target 2019
Onshore wind project J321, Sanilac County
Onshore wind
151 MWWithdrawn / abandoned Sanilac, MIMISO Jan 2014target 2015
Onshore wind project J076, Howard County
Onshore wind
151 MWWithdrawn / abandoned Howard, INMISO Oct 2009target 2012
Onshore wind project J125, Macon County
Onshore wind
151 MWWithdrawn / abandoned Macon, ILMISO Aug 2011target 2014
Onshore wind project J1195, Branch County
Onshore wind
150 MWWithdrawn / abandoned Branch, MIMISO Apr 2019target 2021
Onshore wind project G762, Mower County
Onshore wind
150 MWWithdrawn / abandoned Mower, MNMISO Mar 2007target 2008
Solar project J1915, Bay County
Solar
150 MWWithdrawn / abandoned Bay, MIMISO Aug 2021target 2023
Solar project J1112, Kosciusko County
Solar
150 MWWithdrawn / abandoned Kosciusko, INMISO Mar 2018target 2021
Solar project J3621, Craighead County
Solar
150 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2028
Solar project J1362, Muskegon County
Solar
150 MWWithdrawn / abandoned Muskegon, MIMISO Apr 2019target 2021
Page 27 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)