United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 263

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 263 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2017-059, Hale County
Solar
90.0 MWWithdrawn / abandoned Hale, TXSPP May 2017target 2019
City Farm Solar Energy
Solar · TerraGen Power, LLC
90.0 MWWithdrawn / abandoned ERCOT Apr 2009target 2050
Battery storage project GEN-2019-046, Woods County
Battery storage
90.0 MWWithdrawn / abandoned Woods, OKSPP May 20192022
Falcon Palm Energy Center
Battery storage
90.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Solar + storage project AG1-380, Jackson County
Solar + storage
90.0 MWWithdrawn / abandoned Jackson, OHPJM Sep 2020target 2023
Gas project J3637, Otsego County
Gas
90.0 MWWithdrawn / abandoned Otsego, MIMISO Apr 2024target 2027
Solar project 668, Mcminn County
Solar
90.0 MWWithdrawn / abandoned Mcminn, TNSoutheast Oct 2024
First Solar - Uvalde Solar
Solar · First Solar
90.0 MWWithdrawn / abandoned ERCOT Dec 2010target 2050
Solar project AE2-275, Madison County
Solar · Geenex Solar, LLC
90.0 MWWithdrawn / abandoned Madison, KYPJM Mar 2019target 2022
Solar project J2286, Polk County
Solar
90.0 MWWithdrawn / abandoned Polk, MNMISO Jul 2021target 2026
Solar project Q10, Kern County
Solar
90.0 MWWithdrawn / abandoned Kern, CAWest Jan 2010target 2016
Battery storage project GEN-2019-062, Butler County
Battery storage
90.0 MWWithdrawn / abandoned Butler, KSSPP May 2019target 2027
Wind Project
Onshore wind
90.0 MWWithdrawn / abandoned Franklin, MEISO-NE Jun 2005target 2010
Onshore wind project GI-0906, Todd County
Onshore wind · Citizens Enterprises
90.0 MWWithdrawn / abandoned Todd, SDWest Feb 2009target 2015
York Run Solar, LLC
Solar · York Run Solar, LLC
90.0 MWWithdrawn / abandoned Chautauqua, NYNYISO Sep 2024
Flat Rock - WF-1
Onshore wind
90.0 MWWithdrawn / abandoned Henry, INPJM Nov 2010target 2021
Solar + storage project AG2-666, Jackson County
Solar + storage
90.0 MWWithdrawn / abandoned Jackson, KYPJM Mar 2021target 2023
Hickling Storage, LLC
Battery storage · Hickling Storage, LLC
90.0 MWWithdrawn / abandoned Steuben, NYNYISO Oct 2024
Battery storage project AG2-224, Essex County
Battery storage
90.0 MWWithdrawn / abandoned Essex, NJPJM Mar 2021target 2022
High Desert Solar PV
Solar
90.0 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2014target 2018
Kce NY 22
Battery storage · KCE NY 22, LLC
90.0 MWWithdrawn / abandoned Suffolk, NYNYISO Feb 2020
Coal project T162, Clinton County
Coal
90.0 MWWithdrawn / abandoned Clinton, PAPJM Jan 2008target 2011
Battery storage project J2015, Tunica County
Battery storage
90.0 MWWithdrawn / abandoned Tunica, MSMISO Aug 2021target 2025
Onshore wind project GI-0814, Liberty County
Onshore wind
90.0 MWWithdrawn / abandoned Liberty, MTWest Jul 2008target 2010
Solar project J2745, Humphreys County
Solar
90.0 MWWithdrawn / abandoned Humphreys, MSMISO Sep 2022target 2026
Chinati Solar Power
Solar · TerraGen Power, LLC
90.0 MWWithdrawn / abandoned ERCOT Apr 2009target 2050
Solar + storage project AH1-092, Halifax County
Solar + storage · Scarlet Oak Solar, LLC
90.0 MWWithdrawn / abandoned Halifax, VAPJM Jul 2021target 2025
Solar project AE2-107, Dekalb County
Solar · DK Solar LLC
90.0 MWWithdrawn / abandoned Dekalb, ILPJM Feb 2019target 2022
Solar project AH1-429, Fleming County
Solar · ACE Development Company, LLC
90.0 MWWithdrawn / abandoned Fleming, KYPJM Sep 2021target 2026
Solar + storage project C3-042, Wallowa County
Solar + storage
90.0 MWWithdrawn / abandoned Wallowa, ORWest May 2023target 2026
Berrians GT II
Gas · NRG Energy, Inc.
90.0 MWWithdrawn / abandoned Queens, NYNYISO Aug 2006
Broad Mountain
Wind + storage
90.0 MWWithdrawn / abandoned Carbon, PAPJM Sep 2017target 2021
Onshore wind project N50, Schuylkill County
Onshore wind
90.0 MWWithdrawn / abandoned Schuylkill, PAPJM Jan 2005target 2006
Solar project J1957, Coahoma County
Solar
90.0 MWWithdrawn / abandoned Coahoma, MSMISO Nov 2021target 2025
Goldenrod Solar
Solar · Granada Solar, LLC (Conti)
90.0 MWWithdrawn / abandoned Herkimer, NYNYISO Aug 2018
Flat Rock-WF-1
Onshore wind
90.0 MWWithdrawn / abandoned Henry, INPJM Nov 2010target 2021
Solar project 436, Greene County
Solar
90.0 MWWithdrawn / abandoned Greene, TNSoutheast Jun 2020
Solar project AC2-173, Winnebago County
Solar
90.0 MWWithdrawn / abandoned Winnebago, ILPJM Mar 2017target 2018
Onshore wind project N49, Cambria County
Onshore wind
90.0 MWWithdrawn / abandoned Cambria, PAPJM Jan 2005target 2006
Onshore wind project GI-1301, Grant County
Onshore wind · Summit Wind Farm
90.0 MWWithdrawn / abandoned Grant, SDWest Mar 2013target 2018
Onshore wind project GI-0921, Tripp County
Onshore wind
90.0 MWWithdrawn / abandoned Tripp, SDWest Jul 2009target 2011
Onshore wind project GI-1102, Blaine County
Onshore wind
90.0 MWWithdrawn / abandoned Blaine, MTWest Feb 2011target 2013
Battery storage project Q411, Maricopa County
Battery storage
90.0 MWWithdrawn / abandoned Maricopa, AZWest Sep 2021target 2025
Solar + storage project C2-202, Millard County
Solar + storage
90.0 MWWithdrawn / abandoned Millard, UTWest May 2022target 2026
Onshore wind project 152, Power County
Onshore wind
90.0 MWWithdrawn / abandoned Power, IDWest Oct 2005target 2006
Solar
Solar
90.0 MWWithdrawn / abandoned Oxford, MEISO-NE May 2020target 2021
Leon River Wind Farm
Onshore wind · Gamesa Energy USA
90.0 MWWithdrawn / abandoned ERCOT Jan 2007target 2050
Downeast Wind
Onshore wind
90.0 MWWithdrawn / abandoned Washington, MEISO-NE Oct 2012target 2019
West Greenbrier
Coal
90.0 MWWithdrawn / abandoned Greenbrier, WVPJM Oct 2004target 2009
Onshore wind project 247, Lake County
Onshore wind · GreenWing Energy, Ltd.
90.0 MWWithdrawn / abandoned Lake, ORWest Nov 2008target 2015
Page 263 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)