πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

ONSHORE WIND Β· PJM

Onshore wind project N49, Cambria County

Onshore wind project N49, Cambria County is a 90.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Cambria County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2005 (completed)
  2. Withdrawn / abandonedApr 2005 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
N49
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Salix-Claysburg 115kV
Location
Cambria County, Pennsylvania
Technology
Wind: 90.0 MW
Total requested
90.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 January 2005
Proposed online date
November 2006
Withdrawn
April 2005

Location

Marker shows the centre of Cambria County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Cambria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem