OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2018 requests) — page 25

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,424226.5 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,424 requests · page 25 of 29
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 61, Lincoln County
Solar
20.0 MWWithdrawn / abandoned Lincoln, WAWest Jun 2018target 2019
Onshore wind project 344, Teton County
Onshore wind
20.0 MWWithdrawn / abandoned Teton, MTWest Jun 2018target 2022
Solar + storage project Company IP, Lyon County
Solar + storage
20.0 MWWithdrawn / abandoned Lyon, NVWest Apr 2018target 2021
Solar project AE1-038, Kent County
Solar
20.0 MWWithdrawn / abandoned Kent, DEPJM Jun 2018target 2020
Hornell Solar
Solar · Invenergy Solar Development North America LLC
20.0 MWWithdrawn / abandoned Steuben, NYNYISO Jul 2018
Solar project Q293, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Sep 2018target 2021
Monarda Solar
Solar · Granada Solar, LLC
20.0 MWWithdrawn / abandoned Herkimer, NYNYISO Aug 2018
Edora C Solar Energy Center
Solar · EDF Renewables Development, Inc.
20.0 MWWithdrawn / abandoned Orange, NYNYISO Jun 2018
Solar project 18-02231, Larimer County
Solar
20.0 MWWithdrawn / abandoned Larimer, COWest Feb 2018target 2020
Mistral Wind Alternative
Onshore wind · Mistral Wind LLC
20.0 MWWithdrawn / abandoned Genesee, NYNYISO Oct 2018
Battery storage project AD2-127, Wayne County
Battery storage
20.0 MWWithdrawn / abandoned Wayne, PAPJM Mar 2018target 2020
Battery storage project J1103, Tuscola County
Battery storage
20.0 MWWithdrawn / abandoned Tuscola, MIMISO Mar 2018target 2021
Battery storage project J1101, Manitowoc County
Battery storage
20.0 MWWithdrawn / abandoned Manitowoc, WIMISO Mar 2018target 2023
Charboneau Solar
Solar · Charboneau Solar, LLC
20.0 MWWithdrawn / abandoned Essex, NYNYISO Oct 2018
Slate Hill 2 Solar
Solar · EDF Renewable Development Inc.
20.0 MWWithdrawn / abandoned Orange, NYNYISO Feb 2018
Solar project AE1-007, Preble County
Solar
20.0 MWWithdrawn / abandoned Preble, OHPJM Apr 2018target 2019
Magruder Solar
Solar · Granada Solar, LLC
20.0 MWWithdrawn / abandoned Ulster, NYNYISO Jan 2018
Epcal 1
Solar · sPower Development Company, LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jan 2018
Sunset Hill Solar
Solar · Sunset Hill Solar, LLC
20.0 MWWithdrawn / abandoned Albany, NYNYISO Feb 2018
Hollyhock Solar
Solar · Hollyhock Solar, LLC
20.0 MWWithdrawn / abandoned Albany, NYNYISO Oct 2018
Solar project AD2-045, Queen Anne's County
Solar
20.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Jan 2018target 2019
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2018target 2022
Solar project 56, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, WAWest May 2018target 2019
Solar project AE1-017, Pulaski County
Solar
20.0 MWWithdrawn / abandoned Pulaski, VAPJM May 2018target 2020
Solar
Solar
20.0 MWWithdrawn / abandoned Franklin, VTISO-NE Apr 2018target 2021
Machias Solar
Solar · Machias Solar, LLC
20.0 MWWithdrawn / abandoned Cattaraugus, NYNYISO Jun 2018
Solar project AE1-187, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2018target 2021
Solar
Solar
19.9 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2018target 2021
Tilton Heights Energy Center
Solar
19.9 MWWithdrawn / abandoned Belknap, NHISO-NE Sep 2018target 2025
Solar project 116, Chesterfield County
Solar
19.9 MWWithdrawn / abandoned Chesterfield, SCSoutheast Oct 2018target 2019
Cody Road
Onshore wind · Hecate Energy Cody Road LLC
19.9 MWWithdrawn / abandoned Madison, NYNYISO Jun 2018
Keay Brook Energy Solar
Solar
19.9 MWWithdrawn / abandoned York, MEISO-NE Sep 2018target 2025
Somerset Solar
Solar · Somerset Solar Development LLC
19.9 MWWithdrawn / abandoned Monroe, NYNYISO May 2018
Black Hill Point Energy Center
Solar
19.9 MWWithdrawn / abandoned Windham, CTISO-NE Sep 2018target 2025
Solar
Solar
19.9 MWWithdrawn / abandoned New London, CTISO-NE Sep 2018target 2023
Solar project 89, Marlboro County
Solar
19.9 MWWithdrawn / abandoned Marlboro, SCSoutheast Mar 2018
Solar project 115, Marlboro County
Solar
19.9 MWWithdrawn / abandoned Marlboro, SCSoutheast Oct 2018target 2019
Arcade Solar
Solar · Arcade Solar, LLC
19.9 MWWithdrawn / abandoned Wyoming, NYNYISO Jun 2018
Cayuga Solar
Solar · Cayuga Solar LLC
19.9 MWWithdrawn / abandoned Tompkins, NYNYISO May 2018
Lyonsdale Solar
Solar · Lyonsdale Biomass, LLC
19.9 MWWithdrawn / abandoned Lewis, NYNYISO Jun 2018
Solar project 118, Marlboro County
Solar
19.9 MWWithdrawn / abandoned Marlboro, SCSoutheast Dec 2018target 2020
Battery storage project AE1-244, Atlantic County
Battery storage
19.8 MWWithdrawn / abandoned Atlantic, NJPJM Sep 2018target 2020
Onshore wind project GEN-2018-065, Madison County
Onshore wind
19.8 MWWithdrawn / abandoned Madison, NESPP Oct 2018target 2027
Solar
Solar
19.8 MWWithdrawn / abandoned Somerset, MEISO-NE Nov 2018target 2022
Solar project AE1-126, Bergen County
Solar
19.8 MWWithdrawn / abandoned Bergen, NJPJM Sep 2018target 2019
Battery storage project AE1-202, Monroe County
Battery storage
19.8 MWWithdrawn / abandoned Monroe, PAPJM Sep 2018target 2020
Holtwood Solar
Solar
19.8 MWWithdrawn / abandoned Lancaster, PAPJM Sep 2018target 2026
Sunbury Solar
Solar
19.8 MWWithdrawn / abandoned Snyder, PAPJM Sep 2018target 2027
Solar project AE1-177, Louisa County
Solar
19.0 MWWithdrawn / abandoned Louisa, VAPJM Sep 2018target 2020
Battery Storage
Battery storage
19.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Jul 2018target 2019
Page 25 of 29

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)