United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOHornell Solar
Hornell Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Steuben County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2018 (completed)
- Withdrawn / abandonedOct 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 743
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Invenergy Solar Development North America LLC
- Connection point (POI)
- Bennett 34.5kV
- Location
- Steuben County, New York
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 16 July 2018
- Withdrawn
- October 2019
Location
Marker shows the centre of Steuben County; the queue data does not give exact sites.
Other requests in Steuben County
- Canisteo WindOnshore wind Β· 291 MW Β· in study
- Gemma Energy StorageBattery storage Β· 200 MW Β· in study
- Prattsburgh Wind FarmOnshore wind Β· 147 MW Β· in study
- CohoctonSolar + storage Β· 130 MW Β· in study
- Bassett Energy StorageBattery storage Β· 79.9 MW Β· in study
- Clear View SolarSolar Β· 20.0 MW Β· in study
- Baron WindsOnshore wind Β· 239 MW Β· built
- Baron WindsOnshore wind Β· 239 MW Β· built
- Morris Ridge Solar Energy CenterSolar Β· 177 MW Β· built
- Morris Ridge Solar Energy CenterSolar Β· 177 MW Β· built
- Eight Point Wind Energy CenterOnshore wind Β· 102 MW Β· built
- Canandaigua Wind FarmOnshore wind Β· 82.5 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem