United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

BATTERY STORAGE Β· PJM

Battery storage project AE1-202, Monroe County

Battery storage project AE1-202, Monroe County is a 19.8 MW battery storage request withdrawn in the PJM interconnection queue, in Monroe County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2018 (completed)
  2. Withdrawn / abandonedNov 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE1-202
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Effort Mountain 12.47 kV
Location
Monroe County, Pennsylvania
Technology
Battery: 19.8 MW
Total requested
19.8 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
Queue status
Withdrawn
Entered queue
26 September 2018
Proposed online date
September 2020
Withdrawn
November 2019

Location

Marker shows the centre of Monroe County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Monroe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem