Queue requests in study in MISO (Midcontinent) — page 25

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,337302.2 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,337 requests · page 25 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J4038, St. Francis County
Solar + storage
80.0 MWIn study St. Francis, ARMISO Jun 2025target 2030
Solar project J2609, Waushara County
Solar
80.0 MWIn study Waushara, WIMISO Sep 2022target 2026
Battery storage project J3924, Branch County
Battery storage
80.0 MWIn study Branch, MIMISO Mar 2025target 2030
Solar project J2986, Arkansas County
Solar
80.0 MWIn study Arkansas, ARMISO Sep 2022target 2025
Battery storage project J2552, Rock Island County
Battery storage
80.0 MWIn study Rock Island, ILMISO Sep 2022target 2026
Solar project J2316, Dickinson County
Solar
77.5 MWIn study Dickinson, MIMISO Sep 2021target 2023
Solar + storage project J3630, East Feliciana Parish County
Solar + storage
77.0 MWIn study East Feliciana Parish, LAMISO Apr 2024target 2028
Gas project J2948, Marshall County
Gas
75.0 MWIn study Marshall, IAMISO Sep 2022target 2024
Solar project J2068, Pierce County
Solar
75.0 MWIn study Pierce, WIMISO Jul 2021target 2024
Battery storage project J2550, Yellow Medicine County
Battery storage
75.0 MWIn study Yellow Medicine, MNMISO Sep 2022target 2030
Surplus; J986
Other
75.0 MWIn study MISO Apr 2022target 2022
Solar project J3590, Humphreys County
Solar
75.0 MWIn study Humphreys, MSMISO Apr 2024target 2028
Solar project J2010, Arkansas County
Solar
75.0 MWIn study Arkansas, ARMISO Aug 2021target 2028
Solar project J4049, Ouachita Parish County
Solar
75.0 MWIn study Ouachita Parish, LAMISO Aug 2025target 2029
Surplus; J495
Battery storage
75.0 MWIn study Kossuth, IAMISO Jul 2025target 2026
Surplus; J1325
Battery storage
72.0 MWIn study Rock, MNMISO Feb 2025target 2027
Solar project J4097, Rock County
Solar
71.5 MWIn study Rock, WIMISO Oct 2025target 2030
Solar project J4101, Jefferson County
Solar
71.0 MWIn study Jefferson, WIMISO Oct 2025target 2028
Solar + storage project J2871, Mississippi County
Solar + storage
70.0 MWIn study Mississippi, ARMISO Oct 2025target 2025
Onshore wind project J3970, Huron County
Onshore wind
70.0 MWIn study Huron, MIMISO Apr 2025target 2029
Solar project J3896, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Onshore wind project J1575, Marshall County
Onshore wind
70.0 MWIn study Marshall, MNMISO Jun 2020target 2028
Solar project J4034, Vigo County
Solar
70.0 MWIn study Vigo, INMISO Jun 2025target 2030
Solar project J3925, Knox County
Solar
70.0 MWIn study Knox, INMISO Feb 2025target 2030
Solar project J2177, Tipton County
Solar
67.0 MWIn study Tipton, INMISO Aug 2021target 2024
Onshore wind project J3976, Fayette County
Onshore wind
66.8 MWIn study Fayette, ILMISO Mar 2025target 2028
Onshore wind project J1998, Franklin County
Onshore wind
66.0 MWIn study Franklin, IAMISO Aug 2021target 2024
Solar project J3529, Mahnomen County
Solar
64.0 MWIn study Mahnomen, MNMISO May 2024target 2028
Replacing 50 MW of Solar with Nuclear; Duane Arnold
Nuclear
64.0 MWIn study Linn, IAMISO Aug 2025target 2029
Solar project J2029, Marquette County
Solar
62.5 MWIn study Marquette, MIMISO Nov 2021target 2024
Surplus; J878
Other
60.0 MWIn study MISO Apr 20212024
Solar project J1889, Linn County
Solar
60.0 MWIn study Linn, IAMISO Aug 2021target 2025
Battery storage project J1863, Otsego County
Battery storage
60.0 MWIn study Otsego, MIMISO Aug 2021target 2024
Battery storage project J1880, Ottawa County
Battery storage
60.0 MWIn study Ottawa, MIMISO Aug 2021target 2024
Battery storage project J2376, Shelby County
Battery storage
60.0 MWIn study Shelby, ILMISO Sep 2022target 2024
Surplus; J1067
Other
60.0 MWIn study White, INMISO May 20222024
Solar project J1649, Mccracken County
Solar
60.0 MWIn study Mccracken, KYMISO Mar 2021target 2025
Solar project J3897, Knox County
Solar
60.0 MWIn study Knox, INMISO Feb 2025target 2030
Onshore wind project J3592, Sunflower County
Onshore wind
57.0 MWIn study Sunflower, MSMISO Apr 2024target 2028
Surplus; J928
Other
55.0 MWIn study Delta, MIMISO Apr 2022target 2025
Replacing 55 MW with 29 MW Natural Gas/Fuel Oil; Blue Lake Unit 3
Gas
55.0 MWIn study Scott, MNMISO May 2024target 2025
Gas project J3213, Hennepin County
Gas
51.0 MWIn study Hennepin, MNMISO Sep 2022target 2026
Surplus; J1751
Solar + storage
50.3 MWIn study Wood, WIMISO May 2025target 2028
Solar project J1604, Henderson County
Solar
50.0 MWIn study Henderson, KYMISO Jul 2020target 2026
Surplus; J1369
Other
50.0 MWIn study Dubois, INMISO Apr 2023target 2024
Solar project J1935, Dane County
Solar
50.0 MWIn study Dane, WIMISO Nov 2021target 2025
Surplus; J1002
Other
50.0 MWIn study Waushara, WIMISO May 2022target 2023
Surplus; G905
Other
50.0 MWIn study Midland, MIMISO Aug 2024target 2026
Solar project J2429, Dane County
Solar
50.0 MWIn study Dane, WIMISO Sep 2022target 2027
Surplus; J1587
Battery storage
50.0 MWIn study Muskegon, MIMISO Jan 2025target 2028
Page 25 of 27

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)