United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 245

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 245 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Middletown Energy Storage
Battery storage · Middletown Energy Storage LLC
100 MWWithdrawn / abandoned Orange, NYNYISO Oct 2024
Onshore wind project 221-D, Uinta County
Onshore wind
100 MWWithdrawn / abandoned Uinta, WYWest May 2008target 2012
Onshore wind project 2007-G9
Onshore wind
100 MWWithdrawn / abandoned West Nov 2007target 2012
Battery storage project 143, King County
Battery storage
100 MWWithdrawn / abandoned King, WAWest Apr 2024target 2027
Solar + storage project J2245, St. Tammany Parish County
Solar + storage
100 MWWithdrawn / abandoned St. Tammany Parish, LAMISO Aug 2021target 2024
Onshore wind project GI-2008-4, Baca County
Onshore wind
100 MWWithdrawn / abandoned Baca, COWest Apr 2008target 2010
Battery storage project GEN-2022-153, Burt County
Battery storage
100 MWWithdrawn / abandoned Burt, NESPP Feb 2023target 2026
Onshore wind project J086, Kandiyohi County
Onshore wind
100 MWWithdrawn / abandoned Kandiyohi, MNMISO Oct 2009target 2012
Battery storage project 736, Malheur County
Battery storage
100 MWWithdrawn / abandoned Malheur, ORWest Sep 2023target 2027
Solar project 465, Bedford County
Solar
100 MWWithdrawn / abandoned Bedford, TNSoutheast Dec 2020
Solar project IC-734, Grady County
Solar
100 MWWithdrawn / abandoned Grady, GASoutheast Sep 2018
Solar project AC2-098, Tazewell County
Solar
100 MWWithdrawn / abandoned Tazewell, VAPJM Mar 2017target 2018
Other project G244, Mower County
Other
100 MWWithdrawn / abandoned Mower, MNMISO Aug 2002target 2005
Battery storage project C4-080, Multnomah County
Battery storage
100 MWWithdrawn / abandoned Multnomah, ORWest May 2024target 2027
Onshore wind project J906, Muskegon County
Onshore wind
100 MWWithdrawn / abandoned Muskegon, MIMISO Jun 2017target 2020
Solar project AD2-176, Mchenry County
Solar
100 MWWithdrawn / abandoned Mchenry, ILPJM Mar 2018target 2021
Solar project 811, Carbon County
Solar
100 MWWithdrawn / abandoned Carbon, UTWest Oct 2016target 2017
Onshore wind project GEN-2007-035, Harmon County
Onshore wind
100 MWWithdrawn / abandoned Harmon, OKSPP Sep 2007target 2009
Onshore wind project 200, Carbon County
Onshore wind · Simpson Ridge Wind Farm, LLC
100 MWWithdrawn / abandoned Carbon, WYWest Feb 2008
NextEra Energy Resources
Onshore wind · NextEra Energy Resources, LLC
100 MWWithdrawn / abandoned Wasco, ORWest Jul 2003target 2004
Solar project IC-330, Taylor County
Solar
100 MWWithdrawn / abandoned Taylor, GASoutheast Jan 2014
Solar project GI-2008-27, Saguache County
Solar
100 MWWithdrawn / abandoned Saguache, COWest Nov 2008target 2014
Battery storage project J2202, Jefferson Davis Parish County
Battery storage
100 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Aug 2021target 2022
Solar + storage project Company MO, Nye County
Solar + storage
100 MWWithdrawn / abandoned Nye, NVWest Feb 2022target 2023
Solar project J2604, Clinton County
Solar
100 MWWithdrawn / abandoned Clinton, ILMISO Sep 2022target 2026
Battery storage project J2236, Howard County
Battery storage
100 MWWithdrawn / abandoned Howard, INMISO Aug 2021target 2024
Onshore wind project R54, Ogle County
Onshore wind
100 MWWithdrawn / abandoned Ogle, ILPJM Dec 2006target 2013
Solar project J1595, St. Martin Parish County
Solar
100 MWWithdrawn / abandoned St. Martin Parish, LAMISO Jun 2020target 2023
Solar project AF2-387, Queen Anne's County
Solar
100 MWWithdrawn / abandoned Queen Anne's, MDPJM Mar 2020target 2023
Battery storage project J1731, Madison County
Battery storage
100 MWWithdrawn / abandoned Madison, INMISO Jun 2020target 2022
Bolthouse Solar (Fka Pumpjack Solar)
Solar
100 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
PV Tortilla-Kramer
Solar
100 MWWithdrawn / abandoned Kern, CACAISO Mar 2008target 2009
Solar project J2542, Clark County
Solar
100 MWWithdrawn / abandoned Clark, INMISO Sep 2022target 2026
Onshore wind project G829, Minnehaha County
Onshore wind
100 MWWithdrawn / abandoned Minnehaha, SDMISO Jul 2007
Solar project Company 137, Clark County
Solar
100 MWWithdrawn / abandoned Clark, NVWest Sep 2014target 2016
Solar + storage project J2855, Lawrence County
Solar + storage
100 MWWithdrawn / abandoned Lawrence, INMISO Sep 2022target 2026
Budbreak Solar I
Solar · Budbreak Solar, LLC
100 MWWithdrawn / abandoned Yates, NYNYISO Aug 2023
Onshore wind project GEN-2006-038N024, Kearney County
Onshore wind
100 MWWithdrawn / abandoned Kearney, NESPP Oct 2006
Solar project GI-2020-04, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Mar 2020target 2023
Solar project AG2-638, Wells County
Solar
100 MWWithdrawn / abandoned Wells, INPJM Mar 2021target 2025
Solar project LGE-GIS-2019-011, Mercer County
Solar
100 MWWithdrawn / abandoned Mercer, KYSoutheast Mar 2019target 2021
Wind + storage project 706, Elmore County
Wind + storage
100 MWWithdrawn / abandoned Elmore, IDWest Mar 2023target 2026
Solar + storage project IC-448, Randolph County
Solar + storage
100 MWWithdrawn / abandoned Randolph, GASoutheast Mar 2016
Onshore wind project G813, Boone County
Onshore wind
100 MWWithdrawn / abandoned Boone, IAMISO Jun 2007target 2009
Solar project AG1-058, Greensville County
Solar
100 MWWithdrawn / abandoned Greensville, VAPJM Jul 2020target 2022
Solar project AG2-361, New Kent County
Solar
100 MWWithdrawn / abandoned New Kent, VAPJM Mar 2021target 2023
Solar + storage project 529, Rankin County
Solar + storage
100 MWWithdrawn / abandoned Rankin, MSSoutheast Jan 2023target 2026
Solar project Company 124, Clark County
Solar
100 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Battery storage project 138, Pima County
Battery storage
100 MWWithdrawn / abandoned Pima, AZWest Sep 2022target 2027
Solar project LGE-GIS-2019-016, Henderson County
Solar
100 MWWithdrawn / abandoned Henderson, KYSoutheast Mar 2019target 2021
Page 245 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)