BATTERY STORAGE Β· MISOBattery storage project J2236, Howard County
Battery storage project J2236, Howard County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Howard County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2236
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Greentown 230 kV
- Location
- Howard County, Indiana
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 6 August 2021
- Proposed online date
- October 2024
- Withdrawn
- October 2024
Location
Marker shows the centre of Howard County; the queue data does not give exact sites.
Other requests in Howard County
- Solar project J1481, Howard CountySolar Β· 200 MW Β· agreement signed
- Solar project J1381, Howard CountySolar Β· 200 MW Β· agreement signed
- Solar project AG2-083, Howard CountySolar Β· 300 MW Β· withdrawn
- Solar project AH1-653, Howard CountySolar Β· 200 MW Β· withdrawn
- Battery storage project J2766, Howard CountyBattery storage Β· 190 MW Β· withdrawn
- Onshore wind project J076, Howard CountyOnshore wind Β· 151 MW Β· withdrawn
- Solar project AF2-189, Howard CountySolar Β· 150 MW Β· withdrawn
- Battery storage project AH1-477, Howard CountyBattery storage Β· 112 MW Β· withdrawn
- Battery storage project AG2-084, Howard CountyBattery storage Β· 100 MW Β· withdrawn