Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 244 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1291, Catahoula Parish County
Solar
100 MWWithdrawn / abandoned Catahoula Parish, LAMISO Apr 2019target 2022
Solar + storage project C1-26, Carbon County
Solar + storage
100 MWWithdrawn / abandoned Carbon, UTWest May 2021target 2024
Battery storage project J2537, Shawano County
Battery storage
100 MWWithdrawn / abandoned Shawano, WIMISO Sep 2022target 2024
Battery Storage
Battery storage
100 MWWithdrawn / abandoned Franklin, MAISO-NE Oct 2021target 2023
Solar project GEN-2017-110, Grant County
Solar
100 MWWithdrawn / abandoned Grant, KSSPP Nov 2017target 2020
Solar + storage project AG1-347, Lunenburg County
Solar + storage
100 MWWithdrawn / abandoned Lunenburg, VAPJM Sep 2020target 2024
Onshore wind project GEN-2008-035, Canadian County
Onshore wind
100 MWWithdrawn / abandoned Canadian, OKSPP May 2008target 2011
Battery storage project J2582, Clark County
Battery storage
100 MWWithdrawn / abandoned Clark, INMISO Sep 2022target 2026
Battery storage project AF2-409, Dorchester County
Battery storage
100 MWWithdrawn / abandoned Dorchester, MDPJM Mar 2020target 2022
Solar project J2162, Leflore County
Solar
100 MWWithdrawn / abandoned Leflore, MSMISO Aug 2021target 2024
North Ridge Wind
Onshore wind · Atlantic Wind, LLC
100 MWWithdrawn / abandoned St. Lawrence, NYNYISO Dec 2015
Solar project 25-IC-AM, Lowndes County
Solar
100 MWWithdrawn / abandoned Lowndes, ALSoutheast
Solar project J2239, Washington County
Solar
100 MWWithdrawn / abandoned Washington, MOMISO Aug 2021target 2024
Onshore wind project G770, Martin County
Onshore wind
100 MWWithdrawn / abandoned Martin, MNMISO Mar 2007target 2008
Onshore wind project 291, Carbon/Utah County
Onshore wind
100 MWWithdrawn / abandoned Carbon/Utah, UTWest Sep 2009target 2013
Dunnigan Hills
Onshore wind
100 MWWithdrawn / abandoned Yolo, CACAISO Apr 2012target 2013
Solar project J2070, St. Croix County
Solar
100 MWWithdrawn / abandoned St. Croix, WIMISO Oct 2021target 2024
Onion Creek Wind
Onshore wind · Bobcat Bluff Wind Project LLC
100 MWWithdrawn / abandoned ERCOT Jan 2011
Battery storage project J3804, Putnam County
Battery storage
100 MWWithdrawn / abandoned Putnam, INMISO Apr 2024target 2028
Solar + storage project GEN-2021-104, Bossier Parish County
Solar + storage
100 MWWithdrawn / abandoned Bossier Parish, LASPP May 2021target 2027
Seneca Wind
Onshore wind
100 MWWithdrawn / abandoned Seneca, OHPJM Dec 2008target 2020
Gas project B38, Montgomery County
Gas
100 MWWithdrawn / abandoned Montgomery, PAPJM Nov 1999
Solar project J969, Tuscola County
Solar
100 MWWithdrawn / abandoned Tuscola, MIMISO Mar 2018target 2020
Shellman Solar
Solar
100 MWWithdrawn / abandoned Randolph, GASoutheast Jul 2018target 2022
Onshore wind project H073, Douglas County
Onshore wind
100 MWWithdrawn / abandoned Douglas, MNMISO Jun 2008target 2011
Solar project C3-157, Bingham County
Solar · PacifiCorp
100 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Solar project AH1-658, Van Wert County
Solar
100 MWWithdrawn / abandoned Van Wert, OHPJM Sep 2021target 2025
Solar project 8277, Lee County
Solar · Masked
100 MWWithdrawn / abandoned Lee, SCSoutheast Aug 2016
Battery storage project J3372, Macoupin County
Battery storage
100 MWWithdrawn / abandoned Macoupin, ILMISO Apr 2024target 2028
Solar project 566928, Forsyth County
Solar
100 MWWithdrawn / abandoned Forsyth, NCSoutheast Jun 2022
Solar project J678, St. Francis County
Solar
100 MWWithdrawn / abandoned St. Francis, ARMISO Jul 2016target 2018
Battery Storage
Battery storage
100 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2023target 2026
Battery storage project 20-085, Marion County
Battery storage
100 MWWithdrawn / abandoned Marion, ORWest May 2020target 2023
Onshore wind project J940, Burleigh County
Onshore wind
100 MWWithdrawn / abandoned Burleigh, NDMISO Jun 2017target 2019
Garden Prairie Energy Facility
Gas
100 MWWithdrawn / abandoned Boone, ILPJM Sep 2008target 2024
Rmu Plant
Gas
100 MWWithdrawn / abandoned Kern, CACAISO Apr 2006target 2008
PV Kramer-Inyokern #1
Solar
100 MWWithdrawn / abandoned Kern, CACAISO Mar 2008target 2009
FRV Leo Solar
Solar
100 MWWithdrawn / abandoned Merced, CACAISO Feb 2010target 2013
Solar project AC2-022, Culpeper County
Solar
100 MWWithdrawn / abandoned Culpeper, VAPJM Jan 2017target 2019
Solar project J1959, St. John The Baptist Parish County
Solar
100 MWWithdrawn / abandoned St. John The Baptist Parish, LAMISO Nov 2021target 2025
Solar project AC2-081, Clarke County
Solar
100 MWWithdrawn / abandoned Clarke, VAPJM Feb 2017target 2019
Solar project J2303, Waushara County
Solar
100 MWWithdrawn / abandoned Waushara, WIMISO Jul 2021target 2024
Solar project AH1-650, Greensville County
Solar
100 MWWithdrawn / abandoned Greensville, VAPJM Sep 2021target 2024
PV Piute-Little Rock
Solar
100 MWWithdrawn / abandoned Los Angeles, CACAISO Mar 2008target 2009
Battery storage project AG2-223, Lucas County
Battery storage
100 MWWithdrawn / abandoned Lucas, OHPJM Mar 2021target 2023
Onshore wind project GEN-2006-038N002, Nuckolls County
Onshore wind
100 MWWithdrawn / abandoned Nuckolls, NESPP Oct 2006
Battery storage project AH1-555, Cuyahoga County
Battery storage
100 MWWithdrawn / abandoned Cuyahoga, OHPJM Sep 2021target 2025
Solar + storage project J1274, Posey County
Solar + storage
100 MWWithdrawn / abandoned Posey, INMISO Apr 2019target 2022
Onshore wind project GEN-2006-038N020, Antelope County
Onshore wind
100 MWWithdrawn / abandoned Antelope, NESPP Oct 2006
Solar project J1955, Walworth County
Solar
100 MWWithdrawn / abandoned Walworth, WIMISO Aug 2021target 2025
Page 244 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)