Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 24

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 24 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AH1-767, Hardin County
Battery storage · RWE Solar Development, LLC
140 MWWithdrawn / abandoned Hardin, OHPJM target 2028
Esker Solar Park
Solar · Headwaters Wind Farm III LLC d/b/a Esker Solar Park LLC and Esker Solar Park II LLC
140 MWWithdrawn / abandoned Delaware, INPJM Mar 2020target 2023
Solar project AE1-228, Lee County
Solar
140 MWWithdrawn / abandoned Lee, ILPJM Sep 2018target 2021
Coal project T152, Scioto County
Coal
140 MWWithdrawn / abandoned Scioto, OHPJM Jan 2008target 2011
Solar project AH2-170, Will County
Solar
140 MWWithdrawn / abandoned Will, ILPJM Mar 2022target 2026
Solar project AG2-188, Cumberland County
Solar · Bear Creek Solar, LLC
140 MWWithdrawn / abandoned Cumberland, VAPJM Feb 2025target 2024
Battery storage project AE2-331, Defiance County
Battery storage
139 MWWithdrawn / abandoned Defiance, OHPJM Mar 2019target 2021
Other project AA1-119
Other
139 MWWithdrawn / abandoned PJM Oct 2014
Onshore wind project AC1-186, Somerset County
Onshore wind
138 MWWithdrawn / abandoned Somerset, PAPJM Oct 2016target 2019
Gas project AB1-111, Lancaster County
Gas
135 MWWithdrawn / abandoned Lancaster, PAPJM Oct 2015target 2019
Solar project AI1-104, Paulding County
Solar
135 MWWithdrawn / abandoned Paulding, OHPJM Aug 2022target 2029
Gas project AE1-070, Will County
Gas · Elwood Energy, LLC
135 MWWithdrawn / abandoned Will, ILPJM Jul 2018target 2020
Gas project X1-080, Prince George County
Gas
135 MWWithdrawn / abandoned Prince George, VAPJM Apr 2011target 2015
Gas project AD2-198, Will County
Gas
135 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
FDS Coke Plant
Other
135 MWWithdrawn / abandoned Lucas, OHPJM May 2008target 2017
Gas project W1-058A_DK1, Butler County
Gas
135 MWWithdrawn / abandoned Butler, OHPJM Mar 2010target 2012
Solar + storage project AE1-055, Hudson County
Solar + storage
134 MWWithdrawn / abandoned Hudson, NJPJM Jul 2018target 2021
Coal project U2-080, Greenup County
Coal
134 MWWithdrawn / abandoned Greenup, KYPJM Jul 2008target 2011
Solar project AF1-316, Grundy County
Solar
132 MWWithdrawn / abandoned Grundy, ILPJM Sep 2019target 2022
Fairfield Renewable Energy Facility
Other
132 MWWithdrawn / abandoned Baltimore City, MDPJM Apr 2009target 2016
Solar + storage project AF2-245, Mason County
Solar + storage
132 MWWithdrawn / abandoned Mason, KYPJM Mar 2020target 2023
Solar + storage project AF1-052, Hudson County
Solar + storage
132 MWWithdrawn / abandoned Hudson, NJPJM Jul 2019target 2024
Onshore wind project Y3-031, Tyrrell County
Onshore wind
131 MWWithdrawn / abandoned Tyrrell, NCPJM Feb 2013target 2016
Gas project AA2-051, Philadelphia County
Gas
130 MWWithdrawn / abandoned Philadelphia, PAPJM Feb 2015target 2018
Onshore wind project U1-051, Clearfield County
Onshore wind
130 MWWithdrawn / abandoned Clearfield, PAPJM Mar 2008target 2011
Solar + storage project AF2-397, Fluvanna County
Solar + storage · Kidds Store II, LLC
130 MWWithdrawn / abandoned Fluvanna, VAPJM Apr 2020target 2023
Solar + storage project AH1-613, City Of Suffolk County
Solar + storage
130 MWWithdrawn / abandoned City Of Suffolk, VAPJM Sep 2021target 2025
Solar project AH1-386, Mecklenburg County
Solar
130 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2021target 2025
Solar project AH1-237, Caroline County
Solar
130 MWWithdrawn / abandoned Caroline, VAPJM Sep 2021target 2024
Onshore wind project S54, Tazewell County
Onshore wind
130 MWWithdrawn / abandoned Tazewell, VAPJM Jun 2007target 2009
Little Alligator Windfarm
Onshore wind
130 MWWithdrawn / abandoned Tyrrell, NCPJM May 2015target 2020
Solar project W1-051, Franklin County
Solar
130 MWWithdrawn / abandoned Franklin, PAPJM Mar 2010target 2012
Lost River WF
Onshore wind
130 MWWithdrawn / abandoned Rockingham, VAPJM Jul 2008target 2018
Solar project AE2-287, Brunswick County
Solar
130 MWWithdrawn / abandoned Brunswick, VAPJM Mar 2019target 2022
Gas project AA2-078, Philadelphia County
Gas
130 MWWithdrawn / abandoned Philadelphia, PAPJM Mar 2015target 2018
Onshore wind project AH1-003, Lasalle County
Onshore wind
130 MWWithdrawn / abandoned Lasalle, ILPJM Apr 2021target 2024
Onshore wind project AH1-295, Mclean County
Onshore wind · Invenergy Wind Development LLC
130 MWWithdrawn / abandoned Mclean, ILPJM Sep 2021target 2025
Onshore wind project R03, Adams County
Onshore wind
130 MWWithdrawn / abandoned Adams, INPJM Aug 2006target 2013
Solar + storage project AH1-539, Hardin County
Solar + storage · Riverlake Energy, LLC
129 MWWithdrawn / abandoned Hardin, OHPJM Mar 2025target 2025
Solar project AG1-133, Spotsylvania County
Solar · Virginia Electric and Power Company
128 MWWithdrawn / abandoned Spotsylvania, VAPJM Sep 2020target 2024
Solar + storage project AF1-293, Fluvanna County
Solar + storage · Kidds Store, LLC
128 MWWithdrawn / abandoned Fluvanna, VAPJM Sep 2019target 2022
Battery storage project AG1-359, City Of Chesapeake County
Battery storage · Fentress Energy Storage, LLC
128 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Sep 2020target 2024
Solar project AG1-027, City Of Suffolk County
Solar
128 MWWithdrawn / abandoned City Of Suffolk, VAPJM Jun 2020target 2024
Solar project AE2-292, Campbell County
Solar · Eno Solar, LLC
127 MWWithdrawn / abandoned Campbell, VAPJM Mar 2019target 2021
Solar project AE2-280, Montgomery County
Solar
127 MWWithdrawn / abandoned Montgomery, VAPJM Mar 2019target 2022
Solar + storage project AF1-099, Clearfield County
Solar + storage · Moonlight Flats Solar Power, LLC
127 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2019target 2022
Onshore wind project R16, Stephenson County
Onshore wind
126 MWWithdrawn / abandoned Stephenson, ILPJM Oct 2006target 2016
Bells Solar
Solar · Bells Solar, LLC
126 MWWithdrawn / abandoned Hertford, NCPJM May 2020target 2024
Murphy Solar
Solar · Murphy Solar, LLC
126 MWWithdrawn / abandoned Hertford, NCPJM Dec 2019target 2022
Solar project AH2-237, Wells County
Solar
125 MWWithdrawn / abandoned Wells, INPJM Mar 2022target 2026
Page 24 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)