United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· PJMOnshore wind project AH1-295, Mclean County
Onshore wind project AH1-295, Mclean County is a 130 MW onshore wind request withdrawn in the PJM interconnection queue, in Mclean County, Illinois, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-295
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Developer
- Invenergy Wind Development LLC
- Connection point (POI)
- Brokaw to Mt Pulaski 345 kV
- Location
- Mclean County, Illinois
- Technology
- Wind: 130 MW
- Total requested
- 130 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- December 2025
- Withdrawn
- July 2025
Location
Marker shows the centre of Mclean County; the queue data does not give exact sites.
Other requests in Mclean County
- Twin Groves Storage IIBattery storage Β· 50.0 MW Β· agreement signed
- Twin Groves Storage IBattery storage Β· 50.0 MW Β· agreement signed
- Surplus; G876/G877Wind + storage Β· 400 MW Β· in study
- Onshore wind project J3991, Mclean CountyOnshore wind Β· 340 MW Β· in study
- Battery storage project AI1-024, Mclean CountyBattery storage Β· 300 MW Β· in study
- Onshore wind project J3681, Mclean CountyOnshore wind Β· 300 MW Β· in study
- Dawson SolarSolar Β· 300 MW Β· in study
- Battery storage project J4118, Mclean CountyBattery storage Β· 250 MW Β· in study
- Battery storage project AI1-023, Mclean CountyBattery storage Β· 200 MW Β· in study
- Onshore wind project J3566, Mclean CountyOnshore wind Β· 198 MW Β· in study
- Bright Stalk Generating FacilityOnshore wind Β· 150 MW Β· in study
- Bright Stalk Generating FacilitySolar Β· 150 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem