Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,857519.1 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,857 requests · page 21 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project T2-062, Utah County
Solar + storage
199 MWIn study Utah, UTWest Sep 2025target 2027
Solar + storage project C3-132, Millard County
Solar + storage
199 MWIn study Millard, UTWest May 2023target 2027
Solar + storage project T2-069, Natrona County
Solar + storage
199 MWIn study Natrona, WYWest Sep 2025target 2028
Battery storage project C2-110, Utah County
Battery storage
199 MWIn study Utah, UTWest May 2022target 2025
Solar + storage project GI-2024-01, Weld County
Solar + storage
199 MWIn study Weld, COWest Apr 2024target 2027
Solar + storage project C1-20, Linn County
Solar + storage · Muddy Creek Energy Park LLC
199 MWPaused / redesign Linn, ORWest May 2021target 2025
Wi-Al2-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2029
Solar + storage project C2-131, Emery County
Solar + storage
199 MWIn study Emery, UTWest May 2022target 2026
Solar + storage project C2-115, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Onshore wind project GI-CS-2025-18, Union County
Onshore wind
199 MWIn study Union, NMWest Sep 2025target 2029
Solar + storage project 25-00403, Nye County
Solar + storage
199 MWIn study Nye, NVWest Jul 2025target 2028
Solar + storage project C2-59, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar project PIS043, Utah County
Solar
199 MWIn study Utah, UTWest Jun 2023target 2026
Solar + storage project C2-56, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar + storage project 5RSC-2024-24, Adams County
Solar + storage
199 MWIn study Adams, COWest Jan 2024target 2027
Onshore wind project GI-CS-2025-07, Kit Carson County
Onshore wind
199 MWIn study Kit Carson, COWest Sep 2025target 2029
Me199SB
Solar + storage
199 MWIn study Luna, NMWest Jun 2025target 2028
Solar + storage project IA-PNM-2023-06, Mckinley County
Solar + storage
199 MWIn study Mckinley, NMWest Dec 2022target 2025
Solar + storage project GI-CS-2025-02, Adams County
Solar + storage
199 MWIn study Adams, COWest Sep 2025target 2031
Pentstemon Solar
Solar + storage
199 MWAgreement signed Santa Fe, NMWest Jul 2021target 2024
Solar + storage project C3-062, Crook County
Solar + storage
199 MWIn study Crook, ORWest May 2023target 2026
Solar + storage project BHCT G33, Pueblo County
Solar + storage
199 MWIn study Pueblo, COWest Jun 2022target 2025
Wi-Al3-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2029
Solar project PIS042, Utah County
Solar
199 MWIn study Utah, UTWest Jun 2023target 2026
Solar project GI-2020-01, Pueblo County
Solar
199 MWPaused / redesign Pueblo, COWest Mar 2020target 2023
Onshore wind project GI-DISIS-2021-07, Prowers County
Onshore wind
199 MWPaused / redesign Prowers, COWest May 2021target 2026
Wi-Al-199SB
Solar + storage
199 MWIn study El Paso, TXWest Jun 2025target 2028
Onshore wind project 782, Bingham County
Onshore wind
199 MWIn study Bingham, IDWest Apr 2025target 2028
Solar + storage project C2-58, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar + storage project T2-060, Utah County
Solar + storage
199 MWIn study Utah, UTWest Sep 2025target 2027
Solar + storage project GI-2024-20, Lincoln County
Solar + storage
199 MWIn study Lincoln, COWest May 2024target 2028
Solar + storage project C3-038, Converse County
Solar + storage
199 MWIn study Converse, WYWest May 2023target 2027
Solar + storage project C2-112, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2025
Battery storage project C2-28, Salt Lake County
Battery storage · Dominguez Grid, LLC
199 MWAgreement signed Salt Lake, UTWest Apr 2022target 2031
Gas project GI-CS-2025-27, Delta County
Gas
199 MWIn study Delta, COWest Oct 2025target 2029
Solar + storage project C1-37, Kittitas County
Solar + storage · Badger Gap PV I, LLC
199 MWPaused / redesign Kittitas, WAWest May 2021target 2024
Solar + storage project C2-158, Crook County
Solar + storage · Mormont Solar, LLC
199 MWAgreement signed Crook, ORWest May 2022target 2032
Solar + storage project C2-173, Lake County
Solar + storage
199 MWIn study Lake, ORWest May 2022target 2026
Battery storage project C2-171, Lake County
Battery storage
199 MWIn study Lake, ORWest May 2022target 2027
Battery storage project C3-187, Marion County
Battery storage
199 MWIn study Marion, ORWest May 2023target 2026
Battery storage project GI-2024-09, Adams County
Battery storage
199 MWIn study Adams, COWest May 2024target 2027
Onshore wind project GI-DISIS-2022-17, Kiowa County
Onshore wind
199 MWPaused / redesign Kiowa, COWest May 2022target 2030
Solar + storage project 785, Juab County
Solar + storage
199 MWIn study Juab, UTWest Apr 2025target 2027
Solar + storage project T2-071, San Juan County
Solar + storage
199 MWIn study San Juan, UTWest Sep 2025target 2028
Onshore wind project T2-027, Cowlitz County
Onshore wind
199 MWIn study Cowlitz, WAWest Sep 2025target 2027
Solar + storage project GI-2024-19, Lincoln County
Solar + storage
199 MWIn study Lincoln, COWest May 2024target 2028
Solar + storage project C1-16, Millard County
Solar + storage · Neptune Solar Energy Park LLC
199 MWPaused / redesign Millard, UTWest May 2021target 2025
Solar project IA-PNM-2023-16, Roosevelt County
Solar
199 MWIn study Roosevelt, NMWest Sep 2023target 2028
Solar + storage project PIS105, Emery County
Solar + storage
199 MWIn study Emery, UTWest Dec 2025target 2026
Onshore wind project GI-CS-2025-26, Kit Carson County
Onshore wind
199 MWIn study Kit Carson, COWest Oct 2025target 2029
Page 21 of 38

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)