United States › Grid › Interconnection queues › New Mexico
ONSHORE WIND · WESTOnshore wind project GI-CS-2025-18, Union County
Onshore wind project GI-CS-2025-18, Union County is a 199 MW onshore wind request in interconnection study in the West interconnection queue, in Union County, New Mexico, connecting to Tri-State Generation and Transmission Association.
- PlanningQueued Sep 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-CS-2025-18
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Clapman - Gladstone 115kV Line
- Location
- Union County, New Mexico
- Technology
- Wind: 199 MW
- Total requested
- 199 MW
- Service type
- Energy only (ERIS)
- Study phase
- Cluster Study
- Queue status
- Active
- Entered queue
- 26 September 2025
- Proposed online date
- December 2029
Location
Marker shows the centre of Union County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Union County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem