Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 21 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3933, Franklin County
Solar
200 MWWithdrawn / abandoned Franklin, IAMISO Feb 2025target 2028
Solar project J670, Panola County
Solar
200 MWWithdrawn / abandoned Panola, MSMISO Jul 2016target 2019
Solar project J2464, Worth County
Solar
200 MWWithdrawn / abandoned Worth, IAMISO Sep 2022target 2027
Onshore wind project J1631, Clark County
Onshore wind
200 MWWithdrawn / abandoned Clark, WIMISO Jun 2020target 2023
Onshore wind project J213, Sangamon County
Onshore wind
200 MWWithdrawn / abandoned Sangamon, ILMISO Apr 2011target 2014
Onshore wind project J1979, Howard County
Onshore wind
200 MWWithdrawn / abandoned Howard, IAMISO Aug 2021target 2025
Onshore wind project G771, Howard County
Onshore wind
200 MWWithdrawn / abandoned Howard, IAMISO May 2011target 2008
Onshore wind project J774, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDMISO Nov 2016target 2019
Solar project J3371, Vermilion County
Solar
200 MWWithdrawn / abandoned Vermilion, ILMISO Apr 2024target 2026
Battery storage project J3689, Montgomery County
Battery storage
200 MWWithdrawn / abandoned Montgomery, INMISO Apr 2024target 2028
Onshore wind project H084, Mclean County
Onshore wind
200 MWWithdrawn / abandoned Mclean, NDMISO Jul 2008target 2010
Solar + storage project J2394, Craighead County
Solar + storage
200 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2025
Solar project J3403, Macon County
Solar
200 MWWithdrawn / abandoned Macon, MOMISO Apr 2024target 2028
Battery storage project J3252, St. Clair County
Battery storage
200 MWWithdrawn / abandoned St. Clair, MIMISO Apr 2024target 2028
Onshore wind project G605, Montgomery County
Onshore wind
200 MWWithdrawn / abandoned Montgomery, INMISO Feb 2006target 2008
Solar project J3096, Henderson County
Solar
200 MWWithdrawn / abandoned Henderson, KYMISO Sep 2022target 2025
Onshore wind project H003, Mcdonough County
Onshore wind
200 MWWithdrawn / abandoned Mcdonough, ILMISO Sep 2010target 2009
Solar project J2774, Ionia County
Solar
200 MWWithdrawn / abandoned Ionia, MIMISO Aug 2024target 2026
Gas project G352, Dakota County
Gas
200 MWWithdrawn / abandoned Dakota, MNMISO Jul 2003target 2011
Solar project J2935, Saginaw County
Solar
200 MWWithdrawn / abandoned Saginaw, MIMISO Sep 2022target 2025
Solar project J3345, Moultrie County
Solar
200 MWWithdrawn / abandoned Moultrie, ILMISO Apr 2024target 2028
Solar project J1527, Ottawa County
Solar
200 MWWithdrawn / abandoned Ottawa, MIMISO Jun 2020target 2026
Battery storage project J2449, Faulkner County
Battery storage
200 MWWithdrawn / abandoned Faulkner, ARMISO Sep 2022target 2026
Onshore wind project J630, Deuel County
Onshore wind
200 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2019
Solar project J1909, Bay County
Solar
200 MWWithdrawn / abandoned Bay, MIMISO Aug 2021target 2023
Battery storage project J3557, Morgan County
Battery storage
200 MWWithdrawn / abandoned Morgan, INMISO Apr 2024target 2028
Battery storage project J3662, Monroe County
Battery storage
200 MWWithdrawn / abandoned Monroe, ILMISO Apr 2024target 2028
Battery storage project J3502, Van Buren County
Battery storage
200 MWWithdrawn / abandoned Van Buren, MIMISO Apr 2024target 2028
Onshore wind project G890, Fillmore County
Onshore wind
200 MWWithdrawn / abandoned Fillmore, MNMISO Oct 2007target 2008
Solar project J2664, Montgomery County
Solar
200 MWWithdrawn / abandoned Montgomery, INMISO Sep 2022target 2026
Battery storage project J3581, Avoyelles Parish County
Battery storage
200 MWWithdrawn / abandoned Avoyelles Parish, LAMISO Apr 2024target 2028
Onshore wind project G614, Emmet County
Onshore wind
200 MWWithdrawn / abandoned Emmet, IAMISO Mar 2006target 2009
Solar project J2319, Huron County
Solar
200 MWWithdrawn / abandoned Huron, MIMISO Aug 2021target 2023
Solar project J1640, Hinds County
Solar
200 MWWithdrawn / abandoned Hinds, MSMISO Jun 2020target 2023
Solar + storage project J2356, Craighead County
Solar + storage
200 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2026
Onshore wind project G670, Faribault County
Onshore wind
200 MWWithdrawn / abandoned Faribault, MNMISO Oct 2010target 2011
Onshore wind project R61, Greene County
Onshore wind
200 MWWithdrawn / abandoned Greene, IAMISO Apr 2009target 2010
Onshore wind project H080, Carroll County
Onshore wind
200 MWWithdrawn / abandoned Carroll, ILMISO Jun 2008target 2010
Solar project J1617, Vermilion County
Solar
200 MWWithdrawn / abandoned Vermilion, ILMISO Jun 2020target 2023
Solar + storage project J3748, Washington County
Solar + storage
200 MWWithdrawn / abandoned Washington, MSMISO Apr 2024target 2028
Solar project J1910, Bay County
Solar
200 MWWithdrawn / abandoned Bay, MIMISO Aug 2021target 2023
Solar project J2349, Jackson County
Solar
200 MWWithdrawn / abandoned Jackson, ILMISO Sep 2022target 2026
Solar project J1560, Iberia Parish County
Solar
200 MWWithdrawn / abandoned Iberia Parish, LAMISO Jun 2020target 2023
Solar project J2805, Fountain County
Solar
200 MWWithdrawn / abandoned Fountain, INMISO Sep 2022target 2026
Onshore wind project J860, Jefferson Davis Parish County
Onshore wind
200 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Jun 2017target 2020
Battery storage project J3771, Sabine Parish County
Battery storage
200 MWWithdrawn / abandoned Sabine Parish, LAMISO Apr 2024target 2028
Solar project J1121, Marathon County
Solar
200 MWWithdrawn / abandoned Marathon, WIMISO Mar 2018target 2021
Onshore wind project G961, Goodhue County
Onshore wind
200 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2011target 2012
Onshore wind project J1837, Shelby County
Onshore wind
200 MWWithdrawn / abandoned Shelby, ILMISO Jun 2020target 2023
Onshore wind project J941, Grant County
Onshore wind
200 MWWithdrawn / abandoned Grant, SDMISO Jun 2017target 2020
Page 21 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)