ONSHORE WIND Β· MISOOnshore wind project R61, Greene County
Onshore wind project R61, Greene County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Greene County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2009 (completed)
- Withdrawn / abandonedFeb 2012 (project stopped here)
- ConsentedFeb 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- R61
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Carroll-Grand Junction 161 kV
- Location
- Greene County, Iowa
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 8 April 2009
- Agreement signed
- 15 February 2012
- Proposed online date
- June 2010
- Withdrawn
- February 2012
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Other requests in Greene County
- Solar project J1313, Greene CountySolar Β· 100 MW Β· agreement signed
- Onshore wind project H096, Greene CountyOnshore wind Β· 50.0 MW Β· built
- Onshore wind project G530, Greene CountyOnshore wind Β· 14.0 MW Β· built
- Onshore wind project R62, Greene CountyOnshore wind Β· 300 MW Β· withdrawn
- Solar project J3148, Greene CountySolar Β· 131 MW Β· withdrawn
- Solar project J2445, Greene CountySolar Β· 50.0 MW Β· withdrawn
- Onshore wind project J093, Greene CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Onshore wind project J118, Greene CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Onshore wind project J092, Greene CountyOnshore wind Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem