United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

BATTERY STORAGE Β· MISO

Battery storage project J3581, Avoyelles Parish County

Battery storage project J3581, Avoyelles Parish County is a 200 MW battery storage request withdrawn in the MISO interconnection queue, in Avoyelles Parish County, Louisiana, connecting to CLECO POWER.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3581
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
Eola - Marksville 138.0kV
Location
Avoyelles Parish County, Louisiana
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 April 2024
Proposed online date
May 2028
Withdrawn
May 2025

Location

Marker shows the centre of Avoyelles Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Avoyelles Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem